2017/11/17 13:30 - 2017/11/17 13:30 - 14:15
Line 5: Line 5:
Participants: Participants: Mark, Takahashi, Arai, Sato, Fabian, Aso, Enzo, Hirata, Ohishi, Shoda, Okutomi
Line 13: Line 14:
 * Type-A:
 * Type-B:
 * Type-Bp:
 * Type-A: On schedule for the cable exchange (a bit faster than expected)
 * Type-B: Preparing for the SR2 assembly.
Line 37: Line 38:
==== Plan for coming weeks ====
 * Mark and Fabian did a huge cleanup of the SR2 area and prepared a workspace for assembling the IM.
 * Fabian did a stocktake of the screws for the SR.
  * We have all we need for the IM, except one type that can be added after the rest of the IP is assembled.
  * We have most of what we need for the rest of the payload, and Hirata-san has ordered the others.
 * Hirata-san worked on SR procurement:
  * Suspension wire
  * SR additional parts (compensation masses, clamps etc)
  * Regular, SDC and BUMAX screws.
  * Additional machining on the BS sapphire prism jig to allow it to be used on the PR/SR mirror box.
  * LBB blade design.
 * Enzo and Kozu-kun (with help from Fujii-kun) worked on export from SUMCON to Matlab, and on filter design.

==== Plan for week of 11/20 ====
 * Holiday on Thu 3/23
 * All at Mitaka.
 * SR procurement, planning (Mark, Hirata-san)
 * SR mass budget (Fabian)
 * BS modeling filter design (Enzo, Kozu-kun)

==== Plan for week of 11/27 ====
 * Fabian at commissioning workshop
 * Hirata-san at Kamioka to work with Mirapro on SRM LBB installation.
 * All others at Kamioka to start SR2 assembly.
Line 41: Line 65:
 * Top rid of PR2 and PR3 vacuum tank were fixed
  * Note that the feedthrough flanges are not closed yet.
  * During the fixing, we accidentally moved the injection beam of the Oplev. Alignment was lost.
  * We need to re-align the main beam. So far, we are planning to do it in the week of the commissioning WS.
 * PR mirror position was measured by FARO.
  * The position of the mirror is off from the design by:
   * PR2: (-9.4, +0.5, -6.4)
   * PR3: (-3.5, -0.5, -4.9)
   * PRM: (+4.7, 4.6, -1.5) Note: PRM is fixed
     Note that these values are relative to the side flange of the vacuum tank at the HR side. x is the norm of the flange surface, and z is the norm of optical bench.
Line 42: Line 77:
 * Release PRM. Setup the oplev
 * WD test
Line 46: Line 83:
 * looking for assembly manual.
Line 50: Line 86:
 * Revise Type-C assembly manual.
=== Watchdog system (Tanaka) ===
 * Revise Type-C assembly [[http://gwwiki.icrr.u-tokyo.ac.jp/JGWwiki/IMC%20Suspension?action=AttachFile&do=view&target=sus2_02_v2.pdf|manual]].
Line 61: Line 96:
 * Incidents:  * Incidents: no incident
Line 64: Line 99:
  * Type-A:
  * Type-B:
  * Type-Bp:
  * Type-A: Crane work
  * Type-B: no Kamioka work
  * Type-Bp: Do not bump the mirror in PRM release.
Line 70: Line 105:
=== Plan for the coming months ===  * We will have a brainstorming on how to swap the payload or mirror quickly in the next week.
Line 74: Line 109:
  * Takahashi:
  * Okutomi:
  * Sato:
  * Ishizaki:
  * Takahashi: 22 - 24
  * Okutomi: 20 - 24
  * Sato: 20 - 24
  * Ishizaki: 20 - 24
Line 82: Line 117:
  * Shoda:   * Shoda: 20 - 22
Line 85: Line 120:
  * Tanaka:   * Tanaka: 20 -22
Line 87: Line 122:
  * Arai (ICRR):   * Arai (ICRR): 20 - 24
Line 91: Line 126:
  * Takahashi:
  * Okutomi:
  * Sato:
  * Ishizaki:
  * Mark:
  * Fabian:
  * Hirata:
  * Enzo:
  * Shoda:
  * Takahashi: 27 - 12/1
  * Okutomi: 29 - 12/1
  * Sato: 27 - 12/1
  * Ishizaki: 27 - 12/1
  * Mark: 27 - 12/1
  * Fabian: 27 - 12/1
  * Hirata: 27 - 12/1
  * Enzo: 27 - 12/1
  * Shoda: 27 - 12/1
Line 103: Line 138:
  * Kozu (ICRR):
  * Arai (ICRR):
  * Kozu (ICRR): 27 - 12/1
  * Arai (ICRR): 27 - 12/1

Agenda/Minutes of the VIS Meeting on 2017/11/17

2017/11/17 13:30 - 14:15

Participants: Mark, Takahashi, Arai, Sato, Fabian, Aso, Enzo, Hirata, Ohishi, Shoda, Okutomi

Progress report

Schedule Chart

Type-A : (PDF,MPP)

Type-B: (PDF,MPP)

  • Type-A: On schedule for the cable exchange (a bit faster than expected)
  • Type-B: Preparing for the SR2 assembly.

Type-A (Takahashi)

Past week report

[X-end]

  • Started the replacement of cables from 15th.
  • Dismounted the pre-isolator.
  • Removed the cables above the F1.
  • Removed some screws from the inside of F1.

[ITM]

  • The items from Akeno and Mitaka were delivered on 14th.
  • Transported the bridge frame from the X-end to the center area on 14th.
  • Lifting up the items to the 2nd floor by MESCO on 17th.

Plan for coming weeks

  • X-end: Reassembly of the EQ stop and the cabling from 20th.
  • Y-end: Connection to the cryo-payload from 27th.

Type B (Mark)

Past week report

  • Mark and Fabian did a huge cleanup of the SR2 area and prepared a workspace for assembling the IM.
  • Fabian did a stocktake of the screws for the SR.
    • We have all we need for the IM, except one type that can be added after the rest of the IP is assembled.
    • We have most of what we need for the rest of the payload, and Hirata-san has ordered the others.
  • Hirata-san worked on SR procurement:
    • Suspension wire
    • SR additional parts (compensation masses, clamps etc)
    • Regular, SDC and BUMAX screws.
    • Additional machining on the BS sapphire prism jig to allow it to be used on the PR/SR mirror box.
    • LBB blade design.
  • Enzo and Kozu-kun (with help from Fujii-kun) worked on export from SUMCON to Matlab, and on filter design.

Plan for week of 11/20

  • Holiday on Thu 3/23
  • All at Mitaka.
  • SR procurement, planning (Mark, Hirata-san)
  • SR mass budget (Fabian)
  • BS modeling filter design (Enzo, Kozu-kun)

Plan for week of 11/27

  • Fabian at commissioning workshop
  • Hirata-san at Kamioka to work with Mirapro on SRM LBB installation.
  • All others at Kamioka to start SR2 assembly.

Type-Bp (Shoda)

Past week report

  • Top rid of PR2 and PR3 vacuum tank were fixed
    • Note that the feedthrough flanges are not closed yet.
    • During the fixing, we accidentally moved the injection beam of the Oplev. Alignment was lost.
    • We need to re-align the main beam. So far, we are planning to do it in the week of the commissioning WS.
  • PR mirror position was measured by FARO.
    • The position of the mirror is off from the design by:
      • PR2: (-9.4, +0.5, -6.4)
      • PR3: (-3.5, -0.5, -4.9)
      • PRM: (+4.7, 4.6, -1.5) Note: PRM is fixed
        • Note that these values are relative to the side flange of the vacuum tank at the HR side. x is the norm of the flange surface, and z is the norm of optical bench.

Plan for coming weeks

  • Release PRM. Setup the oplev
  • WD test

OMMT & OSTM (Ohishi)

Past week report

  • Checked and ordered missing parts of hanging jig.
  • Checked glueing jig parts.

Plan for coming weeks

  • Order some glueing jig parts that have defect.
  • Revise Type-C assembly manual.

Past week report

Plan for coming weeks

Other site works

  • Crane inspection: Nov. 22 11:30 - 12:30
  • Commissioning Workshop: Nov. 27 to Dec. 1st

Safety

  • Incidents: no incident
  • Foreseen risks
    • Type-A: Crane work
    • Type-B: no Kamioka work
    • Type-Bp: Do not bump the mirror in PRM release.

Discussion

  • We will have a brainstorming on how to swap the payload or mirror quickly in the next week.

Travel Plans

  • Travel (Week of 11/20):
    • Takahashi: 22 - 24
    • Okutomi: 20 - 24
    • Sato: 20 - 24
    • Ishizaki: 20 - 24
    • Mark:
    • Fabian:
    • Hirata:
    • Enzo:
    • Shoda: 20 - 22
    • Ohishi:
    • Fujii:
    • Tanaka: 20 -22
    • Kozu (ICRR):
    • Arai (ICRR): 20 - 24
  • Travel (Week of 11/27):
    • Takahashi: 27 - 12/1
    • Okutomi: 29 - 12/1
    • Sato: 27 - 12/1
    • Ishizaki: 27 - 12/1
    • Mark: 27 - 12/1
    • Fabian: 27 - 12/1
    • Hirata: 27 - 12/1
    • Enzo: 27 - 12/1
    • Shoda: 27 - 12/1
    • Ohishi:
    • Fujii:
    • Tanaka:
    • Kozu (ICRR): 27 - 12/1
    • Arai (ICRR): 27 - 12/1

Next meeting

On 2017/11/24(Fri)