Size: 2295
Comment:
|
Size: 3006
Comment:
|
Deletions are marked like this. | Additions are marked like this. |
Line 41: | Line 41: |
* Top rid of PR2 and PR3 vacuum tank were fixed * Note that the feedthrough flanges are not closed yet. * During the fixing, we accidentally moved the injection beam of the Oplev. Alignment was lost. * We need to re-align the main beam. So far, we are planning to do it in the week of the commissioning WS. * PR mirror position was measured by FARO. * The position of the mirror is off from the design by: * PR2: (-9.4, +0.5, -6.4) * PR3: (-3.5, -0.5, -4.9) * PRM: (**, 4.6, -1.5) Note: PRM is fixed Note that these values are relative to the side flange of the vacuum tank at the HR side. x is the norm of the flange surface, and z is the norm of optical bench. |
|
Line 42: | Line 53: |
* Release PRM. Setup the oplev * WD test |
|
Line 50: | Line 63: |
=== Watchdog system (Tanaka) === |
Agenda/Minutes of the VIS Meeting on 2017/11/17
2017/11/17 13:30 -
Participants:
Progress report
Schedule Chart
- Type-A:
- Type-B:
- Type-Bp:
Type-A (Takahashi)
Past week report
[X-end]
- Started the replacement of cables from 15th.
- Dismounted the pre-isolator.
- Removed the cables above the F1.
- Removed some screws from the inside of F1.
[ITM]
- The items from Akeno and Mitaka were delivered on 14th.
- Transported the bridge frame from the X-end to the center area on 14th.
- Lifting up the items to the 2nd floor by MESCO on 17th.
Plan for coming weeks
- X-end: Reassembly of the EQ stop and the cabling from 20th.
- Y-end: Connection to the cryo-payload from 27th.
Type B (Mark)
Past week report
Plan for coming weeks
Type-Bp (Shoda)
Past week report
- Top rid of PR2 and PR3 vacuum tank were fixed
- Note that the feedthrough flanges are not closed yet.
- During the fixing, we accidentally moved the injection beam of the Oplev. Alignment was lost.
- We need to re-align the main beam. So far, we are planning to do it in the week of the commissioning WS.
- PR mirror position was measured by FARO.
- The position of the mirror is off from the design by:
- PR2: (-9.4, +0.5, -6.4)
- PR3: (-3.5, -0.5, -4.9)
- PRM: (**, 4.6, -1.5) Note: PRM is fixed
- Note that these values are relative to the side flange of the vacuum tank at the HR side. x is the norm of the flange surface, and z is the norm of optical bench.
- The position of the mirror is off from the design by:
Plan for coming weeks
- Release PRM. Setup the oplev
- WD test
OMMT & OSTM (Ohishi)
Past week report
- Checked and ordered missing parts of hanging jig.
- Checked glueing jig parts.
Plan for coming weeks
- Order some glueing jig parts that have defect.
Revise Type-C assembly manual.
Past week report
Plan for coming weeks
Other site works
- Crane inspection: Nov. 22 11:30 - 12:30
- Commissioning Workshop: Nov. 27 to Dec. 1st
Safety
- Incidents:
- Foreseen risks
- Type-A:
- Type-B:
- Type-Bp:
Discussion
Plan for the coming months
Travel Plans
- Travel (Week of 11/20):
- Takahashi:
- Okutomi:
- Sato:
- Ishizaki:
- Mark:
- Fabian:
- Hirata:
- Enzo:
- Shoda:
- Ohishi:
- Fujii:
- Tanaka:
- Kozu (ICRR):
- Arai (ICRR):
- Travel (Week of 11/27):
- Takahashi:
- Okutomi:
- Sato:
- Ishizaki:
- Mark:
- Fabian:
- Hirata:
- Enzo:
- Shoda:
- Ohishi:
- Fujii:
- Tanaka:
- Kozu (ICRR):
- Arai (ICRR):
Next meeting
On 2017/11/24(Fri)