Agenda/Minutes of the VIS Meeting on 2017/11/17

2017/11/17 13:30 -

Participants:

Progress report

Schedule Chart

Type-A : (PDF,MPP)

Type-B: (PDF,MPP)

  • Type-A:
  • Type-B:
  • Type-Bp:

Type-A (Takahashi)

Past week report

[X-end]

  • Started the replacement of cables from 15th.
  • Dismounted the pre-isolator.
  • Removed the cables above the F1.
  • Removed some screws from the inside of F1.

[ITM]

  • The items from Akeno and Mitaka were delivered on 14th.
  • Transported the bridge frame from the X-end to the center area on 14th.
  • Lifting up the items to the 2nd floor by MESCO on 17th.

Plan for coming weeks

  • X-end: Reassembly of the EQ stop and the cabling from 20th.
  • Y-end: Connection to the cryo-payload from 27th.

Type B (Mark)

Past week report

Plan for coming weeks

Type-Bp (Shoda)

Past week report

  • Top rid of PR2 and PR3 vacuum tank were fixed
    • Note that the feedthrough flanges are not closed yet.
    • During the fixing, we accidentally moved the injection beam of the Oplev. Alignment was lost.
    • We need to re-align the main beam. So far, we are planning to do it in the week of the commissioning WS.
  • PR mirror position was measured by FARO.
    • The position of the mirror is off from the design by:
      • PR2: (-9.4, +0.5, -6.4)
      • PR3: (-3.5, -0.5, -4.9)
      • PRM: (+4.7, 4.6, -1.5) Note: PRM is fixed
        • Note that these values are relative to the side flange of the vacuum tank at the HR side. x is the norm of the flange surface, and z is the norm of optical bench.

Plan for coming weeks

  • Release PRM. Setup the oplev
  • WD test

OMMT & OSTM (Ohishi)

Past week report

  • Checked and ordered missing parts of hanging jig.
  • Checked glueing jig parts.

Plan for coming weeks

  • Order some glueing jig parts that have defect.
  • Revise Type-C assembly manual.

Past week report

Plan for coming weeks

Other site works

  • Crane inspection: Nov. 22 11:30 - 12:30
  • Commissioning Workshop: Nov. 27 to Dec. 1st

Safety

  • Incidents:
  • Foreseen risks
    • Type-A:
    • Type-B:
    • Type-Bp:

Discussion

Plan for the coming months

Travel Plans

  • Travel (Week of 11/20):
    • Takahashi: 22 - 24
    • Okutomi: 20 - 24
    • Sato: 20 - 24
    • Ishizaki: 20 - 24
    • Mark:
    • Fabian:
    • Hirata:
    • Enzo:
    • Shoda: 20 - 22
    • Ohishi:
    • Fujii:
    • Tanaka: 20 -22
    • Kozu (ICRR):
    • Arai (ICRR): 20 - 24
  • Travel (Week of 11/27):
    • Takahashi: 27 - 12/1
    • Okutomi: 29 - 12/1
    • Sato: 27 - 12/1
    • Ishizaki: 27 - 12/1
    • Mark: 27 - 12/1
    • Fabian: 27 - 12/1
    • Hirata: 27 - 12/1
    • Enzo: 27 - 12/1
    • Shoda: 27 - 12/1
    • Ohishi:
    • Fujii:
    • Tanaka:
    • Kozu (ICRR): 27 - 12/1
    • Arai (ICRR): 27 - 12/1

Next meeting

On 2017/11/24(Fri)