= Agenda/Minutes of the VIS Meeting on 2017/11/17 = 2017/11/17 13:30 - 14:15 Participants: Mark, Takahashi, Arai, Sato, Fabian, Aso, Enzo, Hirata, Ohishi, Shoda, Okutomi == Progress report == === Schedule Chart === Type-A : ([[TBD|PDF]],[[TBD|MPP]]) Type-B: ([[TBD|PDF]],[[TBD|MPP]]) * Type-A: On schedule for the cable exchange (a bit faster than expected) * Type-B: Preparing for the SR2 assembly. === Type-A (Takahashi) === ==== Past week report ==== [X-end] * Started the replacement of cables from 15th. * Dismounted the pre-isolator. * Removed the cables above the F1. * Removed some screws from the inside of F1. [ITM] * The items from Akeno and Mitaka were delivered on 14th. * Transported the bridge frame from the X-end to the center area on 14th. * Lifting up the items to the 2nd floor by MESCO on 17th. ==== Plan for coming weeks ==== * X-end: Reassembly of the EQ stop and the cabling from 20th. * Y-end: Connection to the cryo-payload from 27th. === Type B (Mark) === ==== Past week report ==== * Mark and Fabian did a huge cleanup of the SR2 area and prepared a workspace for assembling the IM. * Fabian did a stocktake of the screws for the SR. * We have all we need for the IM, except one type that can be added after the rest of the IP is assembled. * We have most of what we need for the rest of the payload, and Hirata-san has ordered the others. * Hirata-san worked on SR procurement: * Suspension wire * SR additional parts (compensation masses, clamps etc) * Regular, SDC and BUMAX screws. * Additional machining on the BS sapphire prism jig to allow it to be used on the PR/SR mirror box. * LBB blade design. * Enzo and Kozu-kun (with help from Fujii-kun) worked on export from SUMCON to Matlab, and on filter design. ==== Plan for week of 11/20 ==== * Holiday on Thu 3/23 * All at Mitaka. * SR procurement, planning (Mark, Hirata-san) * SR mass budget (Fabian) * BS modeling filter design (Enzo, Kozu-kun) ==== Plan for week of 11/27 ==== * Fabian at commissioning workshop * Hirata-san at Kamioka to work with Mirapro on SRM LBB installation. * All others at Kamioka to start SR2 assembly. === Type-Bp (Shoda) === ==== Past week report ==== * Top rid of PR2 and PR3 vacuum tank were fixed * Note that the feedthrough flanges are not closed yet. * During the fixing, we accidentally moved the injection beam of the Oplev. Alignment was lost. * We need to re-align the main beam. So far, we are planning to do it in the week of the commissioning WS. * PR mirror position was measured by FARO. * The position of the mirror is off from the design by: * PR2: (-9.4, +0.5, -6.4) * PR3: (-3.5, -0.5, -4.9) * PRM: (+4.7, 4.6, -1.5) Note: PRM is fixed Note that these values are relative to the side flange of the vacuum tank at the HR side. x is the norm of the flange surface, and z is the norm of optical bench. ==== Plan for coming weeks ==== * Release PRM. Setup the oplev * WD test === OMMT & OSTM (Ohishi) === ==== Past week report ==== * Checked and ordered missing parts of hanging jig. * Checked glueing jig parts. ==== Plan for coming weeks ==== * Order some glueing jig parts that have defect. * Revise Type-C assembly [[http://gwwiki.icrr.u-tokyo.ac.jp/JGWwiki/IMC%20Suspension?action=AttachFile&do=view&target=sus2_02_v2.pdf|manual]]. ==== Past week report ==== ==== Plan for coming weeks ==== === Other site works === * Crane inspection: Nov. 22 11:30 - 12:30 * Commissioning Workshop: Nov. 27 to Dec. 1st === Safety === * Incidents: no incident * Foreseen risks * Type-A: Crane work * Type-B: no Kamioka work * Type-Bp: Do not bump the mirror in PRM release. == Discussion == * We will have a brainstorming on how to swap the payload or mirror quickly in the next week. == Travel Plans == * Travel (Week of 11/20): * Takahashi: 22 - 24 * Okutomi: 20 - 24 * Sato: 20 - 24 * Ishizaki: 20 - 24 * Mark: * Fabian: * Hirata: * Enzo: * Shoda: 20 - 22 * Ohishi: * Fujii: * Tanaka: 20 -22 * Kozu (ICRR): * Arai (ICRR): 20 - 24 * Travel (Week of 11/27): * Takahashi: 27 - 12/1 * Okutomi: 29 - 12/1 * Sato: 27 - 12/1 * Ishizaki: 27 - 12/1 * Mark: 27 - 12/1 * Fabian: 27 - 12/1 * Hirata: 27 - 12/1 * Enzo: 27 - 12/1 * Shoda: 27 - 12/1 * Ohishi: * Fujii: * Tanaka: * Kozu (ICRR): 27 - 12/1 * Arai (ICRR): 27 - 12/1 == Next meeting == On 2017/11/24(Fri)