= Agenda/Minutes of the VIS Meeting on 2017/11/24 = 2017/11/24 13:30 - 15:00 Participants: Enzo, Shoda, Takahashi, Ohishi, Arai, Sato, Okutomi, Aso, Mark, Hirata, Fabian, Tanaka, Raffaele == Progress report == === Schedule Chart === Type-A : ([[TBD|PDF]],[[TBD|MPP]]) Type-B: ([[TBD|PDF]],[[TBD|MPP]]) * Type-A: On schedule for the cable replacement (2 days delay expected in the next week) * Type-B: * Type-Bp: === Type-A (Takahashi) === ==== Past week report ==== [X-end] * Recovered from the blackout. * Lifted down the EQ stop to release the bottom stopper for BF. * Set the F2 stage on the frame lock and cabled between F1 and F2. * Suspended the filter chain from the F1, and checked the load for F1. * Set the F1 stage on the frame lock and extended the EQ stop. * Started the cabling between F0 and F1. * Set the top ring onto the frame lock. ==== Plan for coming weeks ==== * X-end: Installation of the pre-isolaotor and reassembly of the BF damper. * Y-end: Connection to the cryo-payload. === Type B (Mark) === ==== Past week report ==== * Mark worked on SR2 planning. * Mark thought through what would be required to swap an optic (e.g., SRM) in situ (JGW-T1707436). * Hirata-san tried removing disks from IM flags (so we could reuse them in flag bases and make a complete set for SR2) but only got 1 of 4 out. * Hirata-san ordered more disks for IM flags. * Hirata-san asked for quotes on SF LBB blades. * Hirata-san got a reduced quote for the LBB damper rings. * Hirata-san received and cleaned suspension wires for the SR. * Fabian worked on the SR mass budget. * Fabian worked out the COM of the SR2 optic, and Mark used it to derive the proper prism positions. * Enzo and Kozu-kun worked on control filter design and installation. ==== Plan for week of 11/27 ==== * Fabian at commissioning workshop * Hirata-san at Kamioka Tue-Fri to work with Mirapro on SRM LBB installation. * All others (Mark, Enzo, Shoda-san, Kozu-kun) at Kamioka to start SR2 assembly. * Mark from Mon lunchtime. * Kozu-kun from Mon lunchtime through Wed. * Mirror gluing. * SR2 rack setup. ==== Plan for week of 12/4 ==== * All at Kamioka * IM assembly and pico test. * Assembly frame alignment and optical table centering. * OL setup. ==== Vacation Info ==== * Mark 12/22-1/3 * Enzo TBD, probably 12/22-1/3 * Fabian 12/22-1/5 * Hirata-san 12/21-22 (conference) === Type-Bp (Shoda) === ==== Past week report ==== * Recovered from the power outage * PRM tried to be released * The suspension hits to the EQ stop. We found that the inner frame was tilted. * We inserted the sims below the Traverser top plate. * The bellows legs of the tank were not perfectly tightened...?? ==== Plan for coming weeks ==== * PRM release trial again * Re-alignment of the main beam === OMMT & OSTM (Ohishi) === ==== Past week report ==== ==== Plan for coming weeks ==== === Watchdog system (Tanaka) === ==== Past week report ==== *I want to start ordering mass production version.-->*Waiting. *The execution of the budget was stopped by AEL. -->Budget execution was allowed.(Meeting at Kamioka.) *Start of order related works.-->Completed(Coop Univ.Tokyo and anther corp.). *Operation test of the testing tool for mass production equipment.-->Completed. *I stay at Toyama on the 19th.And experiment in Kamioka from 20th to 22nd.-->20th I could't experiment by power outage.21th Completed the connection experiment with the digital system. 22nd The cutoff operation test does not go well.--> *DC power supply fault(?). *I can't see the driver output and sensor output. ==== Plan for coming weeks ==== *Plan the operation test again at KAGRA. *Retest in Mitaka. *Start ordering mass production version.-->Start preparations. === Other site works === * Commissioning Workshop: Nov. 27 to Dec. 1st === Safety === * Incidents: Dropped a nut inside the PRM chamber. * Foreseen risks * Type-A: Crane work * Type-B: No heavy work expected * Type-Bp: Be careful with the PRM release. == Discussion == === Brainstorming on how to exchange the payload part without completely disassembling the suspension chain === * [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7077|Type-B assembly drawings]] *[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=5816|Type-Bp drawings]] * Two possible methods * Common part: pull out the suspension from the chamber and put it on the assembly frame. * Mark's idea: Make smaller winch systems for TM hanging, which can be used with the BF sitting above the IM. * How to align the suspension chain with the sliding rails of the assembly frame is a challenge. * Shoda-san's idea: Unhook the rod connecting the BF and IM. Then remove the top part (down to BF) and put it temporarily in the chamber. * Is unhooking possible ? * Alignment of the top part with the payload part when connecting again may be a challenge. * IMRM adjustment may be difficult. * Conclusion: We should think about the ideas presented today and discuss it again in the next meeting to decide the next action. == Travel Plans == * Travel (Week of 11/27): * Takahashi: 27 - 12/1 * Okutomi: 29 - 12/1 * Sato: 27 - 12/1 * Ishizaki: 28 - 12/1 (?) * Mark: 27 - 12/1 * Fabian: 27 - 12/1 * Hirata: 28 - 12/1 * Enzo: 27 - 12/1 * Shoda: 27 - 12/1 * Ohishi: * Fujii: * Tanaka: * Kozu (ICRR): 27 - 29 * Arai (ICRR): 27 - 12/1 * Travel (Week of 12/4): * Takahashi: 4 - 8 * Okutomi: 4 - 8 * Sato: 4 - 8 * Ishizaki: 4 - 8 * Mark: 4 - 8 * Fabian: 5 - 8 * Hirata: 4 - 8 * Enzo: * Shoda: * Ohishi: * Fujii: * Tanaka: * Kozu (ICRR): ? * Arai (ICRR): == Next meeting == On 2017/12/1(Fri)