Line 35: Line 35:
 *Retest in Mitaka.-->There is no problem in operation test at all.
 *Continuous operation test(Over 100 hours).-->
   *Temperature rise.-->No problem.
   *WD operation.-->No problem.
 
 *Start ordering mass production version.-->Ongoing(Formal request for quotation from the vendors.).
Line 36: Line 43:
 *Plan the operation test again at KAGRA-->
   *Actual test of WD operation(Retest).
   *I would like to experiment with the next schedule.
     *Toyama on 4th,From 5th to 7th Kamioka,8th(preparatory day,Toyama-->Tokyo).

Agenda/Minutes of the VIS Meeting on 2017/12/1

2017/12/1 13:30 -

Participants:

Progress report

Schedule Chart

Type-A : (PDF,MPP)

Type-B: (PDF,MPP)

  • Type-A:
  • Type-B:
  • Type-Bp:

Type-A (Takahashi)

Past week report

Plan for coming weeks

Type B (Mark)

Past week report

Plan for coming weeks

Type-Bp (Shoda)

Past week report

Plan for coming weeks

OMMT & OSTM (Ohishi)

Past week report

Plan for coming weeks

Watchdog system (Tanaka)

Past week report

  • Retest in Mitaka.-->There is no problem in operation test at all.

  • Continuous operation test(Over 100 hours).-->

    • Temperature rise.-->No problem.

    • WD operation.-->No problem.

  • Start ordering mass production version.-->Ongoing(Formal request for quotation from the vendors.).

Plan for coming weeks

  • Plan the operation test again at KAGRA-->

    • Actual test of WD operation(Retest).
    • I would like to experiment with the next schedule.
      • Toyama on 4th,From 5th to 7th Kamioka,8th(preparatory day,Toyama-->Tokyo).

Other site works

  • Commissioning Workshop: Nov. 27 to Dec. 1st

Safety

  • Incidents:
  • Foreseen risks
    • Type-A:
    • Type-B:
    • Type-Bp:

Discussion

2nd Brainstorming on how to exchange the payload part without completely disassembling the suspension chain

Travel Plans

  • Travel (Week of 12/4):
    • Takahashi: 4 - 8
    • Okutomi: 4 - 8
    • Sato: 4 - 8
    • Ishizaki: 4 - 8
    • Mark: 4 - 8
    • Fabian: 5 - 8
    • Hirata: 4 - 8
    • Enzo:
    • Shoda:
    • Ohishi:
    • Fujii:
    • Tanaka:
    • Kozu (ICRR): 7
    • Arai (ICRR):
  • Travel (Week of 12/11):
    • Takahashi:
    • Okutomi:
    • Sato:
    • Ishizaki:
    • Mark:
    • Fabian:
    • Hirata:
    • Enzo:
    • Shoda:
    • Ohishi:
    • Fujii:
    • Tanaka:
    • Kozu (ICRR):
    • Arai (ICRR):

Next meeting

On 2017/12/8(Fri)