= Agenda/Minutes of the VIS Meeting on 2017/12/1 = 2017/12/1 13:30 - 14:40 Participants: Mark, Hirata, Ohishi, Arai, Fabian, Aso, Enzo, Ishizaki, Takahashi, Sato, Tanaka, Okutomi == Progress report == === Schedule Chart === Type-A : ([[TBD|PDF]],[[TBD|MPP]]) Type-B: ([[TBD|PDF]],[[TBD|MPP]]) * Type-A: 1 week delay * Type-B: Waiting for the schedule === Type-A (Takahashi) === ==== Past week report ==== [X-end] * Checked the ACCs with the drivers. [Y-end] * Replaced the blades for FR in the BF. * Pre-assemled the maraging wire for the cryo-payload with the junction box. * Inserted the wire from the cryostat. * Hooked the wire on the BF. * Installed the cryo-payload into the cryostst. * Suspended the cryo-payload from the BF. * Tuned the BF and the F3. * Applied the cabling between the BF and the cryo-payload. ==== Plan for coming weeks ==== * X-end: Installation of the pre-isolaotor and reassembly of the BF damper. * Y-end: Align the cryo-payload by the FR and the picomotor in the BF. === Type B (Mark) === ==== Past week report ==== * We brought the SR2 optic into the tunnel and moved it into the good mirror box. The spare mirror was moved into the not-so-good mirror box. * Enzo assembled the SR2 rack and laid all the long cables from the rack into the cleanbooth. (Hayakawa-san can now proceed with the rebuilding of the changing cleanbooth.) * Mark and Shoda-san took data for calibrating and diagonalizing the OL. (Due to the odd angle of the first steering mirror, the beam pattern is rotated by 62° at the QPD.) * Enzo found nearly all in-vacuum cables. * Enzo and Shoda-san got several more loops closed on the BS. * Mark found three geophone pods and two feedthrough adapters for SR2 (now have 3 FAs but need 4). * Mark took out S-numbers for anonymous boxes in the SR2 and put yellow stickers supplied by Tomura-san on them. * Hirata-san worked on SR procurement. * Hirata-san worked with Mirapro to get the SRM LBB installed in the tank. ==== Plan for week of 12/4 ==== * Mark at Kamioka. * Fabian at f2f satellite meeting Mon, then Kamioka. * Enzo at f2f then Mitaka. * Hirata-san at Kamioka Mon-Thu, Mitaka Fri. * Kozu-kun Thu only. * Mirror gluing. * IM assembly and pico test. ==== Plan for week of 12/11 ==== * Mark, Fabian, Enzo, Hirata-san, Shoda-san at Kamioka. * Kozu-kun Mon-Thu only. * Assembly frame alignment and optical table centering. * Move trolley system from SR3. * OL setup. ==== Plan for week of 12/18 ==== * Shoda-san vacation * Mark, Fabian, Enzo, Kozu-kun at Kamioka Mon-Wed. ==== Vacation Info ==== * Mark 12/22-1/3 * Enzo TBD, probably 12/22-1/3 * Fabian 12/22-1/5 * Hirata-san 12/21-22 (conference) * Shoda-san 12/18-21 === Type-Bp (Shoda) === ==== Past week report ==== * PRM inner frame fixed * We found the fixing on the vacuum tank legs are not perfect. * Mirapro people jacked up the inner frame to insert the sims. And fixed the inner frame. (The vacuum tank was not fixed.) The floor level is not nice. * Inner frame is now leveled and removed the sims on the Traverser stages. * PRM released * The suspension was released. As far as looking at the spectra, the suspension is not touching. * The transfer functions should be checked. * PR3 again largely tilted * OSEM DC position change is again required. ==== Plan for coming weeks ==== * F2F * Asked Ohishi-san to work on the adjustment of the OSEMs. === OMMT & OSTM (Ohishi) === ==== Past week report ==== * Checked in-vac cable number. Possible change of mirror actuator from coil to OSEM, makes the number of cables increase than expected. * Received quotation from FCL. Need to fix some minor problems. ==== Plan for coming weeks ==== * Resume evaluation of OSEMs. === Watchdog system (Tanaka) === ==== Past week report ==== *Retest in Mitaka.-->There is no problem in operation test at all. *Continuous operation test(Over 100 hours).--> *Temperature rise.-->No problem. *WD operation.-->No problem. *Start ordering mass production version.-->Ongoing(Formal request for quotation from the vendors.). ==== Plan for coming weeks ==== *Plan the operation test again at KAGRA--> *Actual test of WD operation(Retest). * The next on site test of the WDS: From 12/12(Tue) - 14(Thu) === Other site works === === Safety === * Incidents: Dropped the BF cap by 1 cm when opening it (Type-A, Y-End) * Foreseen risks * Type-A: Crane work * Type-B: Crane work * Type-Bp: No heavy work == Discussion == === 2nd Brainstorming on how to exchange the payload part without completely disassembling the suspension chain === * Postponed to the next week == Travel Plans == * Travel (Week of 12/4): * Takahashi: 4 - 8 * Okutomi: 4 - 8 * Sato: 4 - 8 * Ishizaki: 4 - 7 * Mark: 4 - 8 * Fabian: 5 - 8 * Hirata: 4 - 7 * Enzo: * Shoda: * Ohishi: * Fujii: * Tanaka: * Kozu (ICRR): 7 * Arai (ICRR): * Travel (Week of 12/11): * Takahashi: 11-15 * Okutomi: 11-15 * Sato: 11-15 * Ishizaki: 11-15 * Mark: 11-15 * Fabian: 11-15 * Hirata: 11-15 * Enzo: 11-15 * Shoda: 11-15 * Ohishi: * Fujii: * Tanaka: 12-14 * Kozu (ICRR): 11-13 * Arai (ICRR): == Next meeting == On 2017/12/8(Fri)