= Agenda/Minutes of the VIS Meeting on 2018/1/12 = 2018/1/12 13:30 - 14:30 Participants: Mark, Shoda, Takahashi, Ohishi, Sato, Fabian, Arai, Kozu, Ishizaki, Enzo, Aso, Hirata == Progress report == === Schedule Chart === Type-A : ([[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7320|PDF/MPP]]) Type-B: ([[TBD|PDF]],[[TBD|MPP]]) === Type-A (Takahashi) === ==== Past week report ==== [X-end] * Replaced the vacuum gauge. * Connected the PT100 sensor to the monitor. * Fastened the top chamber and the hatch on the cross tube. * Started evacuation of EXV chamber on the 28th in Dec. The present pressure is 78Pa. * Transported the items to the center room (footholds, workbench, chain bolocks, tools, etc.) [Y-end] * Transported the dummy payload to the center room. [X-front] * Lifted up the items from the X/Y-end. ==== Plan for coming weeks ==== * The evacuation of EYV chamber will be started in the 19th morning. * Prepare to start assembly of DF in the clean booth. * The short rod for DP is missing. * The assembly of pre-isolaor for SRM is planed. === Type B (Mark) === ==== Report for week of 12/25 ==== * Hirata-san got the L-brackets machined and washed, and installed them on the IM ring bars. * Shoda-san recovered the BS from the power outage on 12/25. * Miyakawa-san fixed an issue with the SR2 RTM which had prevented it from running. * Shoda-san, Hirata-san and Kozu-kun cleaned the assembly frame and installed new jack receptacles on the load gauge adapter. * They weighed the IM without ballast masses, and then added the lower masses and installed the IM on the assembly frame. * They installed the winch system on the IM, and inspected the clamp pieces for possible scratches. * They ran cables for the SR2 steppers and OSEMs. * They calibrated the BF LVDT. ==== Report for week of 1/4 ==== * Mark fixed a number of errors with the Type B screens. ==== Report for week of 1/9 ==== * We weighed the mirror in its box (and later the empty box), and the RM. * Fabian worked on the SR2/SR3/SRM mass budget and did an inventory of spare ballast masses. * We hung the SR2 and RM. * We assembled the bottom section of the security structure below the RM. * We cabled the RM OSEMs up to the IM. * Hirata-san gave up on waiting for a third quote for the blades and blade parts and started the ordering process. * Hirata-san got rod cable clamp parts from Takahashi-san and worked on drawings for the improved BS vertical and yaw adjusters. ==== Plan for week of 1/15 ==== * Fabian at Mitaka Monday 1/15 to inspect filter load test items. * All at Kamioka. * Shoda-san to work on making OSEMs - Enzo and Kozu-kun to help and learn. * Test RM OSEMs. * Check coil driver is successfully driving current. * Time permitting, do TF test from coils to OL pitch and yaw. * Suspend IM using load gauge adapter, and check/adjust total mass and balance. ==== Plan for week of 1/22 ==== * All at Kamioka * Bring in BF and suspend IM. * Route final RM/IM cables up to below BF. * Recheck/adjust total mass and balance. * Route selected cables to flange. * Test IM picos and BF yaw pico. ==== Plan for week of 1/29 ==== * Enzo at Mitaka 1/29 and most of 1/30, then vacation. * Kozu-kun away. * All others at Kamioka. * Build IRM around IM. * Cable/test/adjust IM OSEMs. * Time permitting, do TFs from IM OSEMs to themselves and to optical sensor. ==== Vacation Info ==== * Enzo 1/30-2/19 (at Mitaka 1/29, part of 1/30) * Kozu-kun 1/29-2/2 === Type-Bp (Shoda) === ==== Past week report ==== ==== Plan for coming weeks ==== === OMMT & OSTM (Ohishi) === ==== Past week report ==== * Talked with Miyakawa-san about digital system for OMMT/OSTM. He will prepare the rack around this spring. * Prepared Al stand for OSEM test. I found that coil wire of a sample OSEM was broken. * Ordered non-magnetic screws for Intermediate Mass. Nabeya Bi-tech Kaisha(NBK) recommend material Ti-6Al-4V. ==== Plan for coming weeks ==== * Aso-san will send remaining (about 40?) OSEMs from Mitaka. * Some parts for hanging jig ordered last year will arrive. * === Watchdog system (Tanaka) === ==== Past week report ==== *Order request has been completed(To order the University of Tokyo).--> Delivery completed. And Digikey's parts delivery completed. *Start other ordering.-->Meeting due to order change procedure to vendor. ==== Plan for coming weeks ==== *Start ordering sequentially for mass products..-->But some adjustment works are necessary. *Preparation for assembly of mass products. === Other site works === * Parking space === Safety === * Incidents: * Touched a mirror suspension wire during assembly * Bumped the back of VOXY * Foreseen risks * Type-A: Crane work * Type-B: Crane work == Discussion == * Commissioning support * Okutomi-kun will available during the initial pump down * Some of the Type-A members will always be in Kamioka. They can operate motors for alignment adjustment. * Lab. temperature * We want to have the same temperature during the assembly and observation * The current temperature (21 deg. ?) is comfortable. == Travel Plans == * Travel (Week of 1/15): * Takahashi: 15 - 19 * Okutomi: 15 - 20 * Sato:15 - 19 * Ishizaki:15 - 19 * Mark: 15 - 19 * Fabian: 16 - 19 * Hirata: 15 - 19 * Enzo: 15 - 19 * Shoda: 15 - 18 * Ohishi: * Fujii: * Tanaka: * Kozu (ICRR): 15 - 19 * Arai (ICRR): 15 - 19 * Travel (Week of 1/22): * Takahashi: 22 - 26 * Okutomi: 21 - 26 * Sato: 22 - 26 * Ishizaki: 22 - 26 * Mark: 22 - 26 * Fabian: 22 - 26 * Hirata: 22 - 26 * Enzo: 22 - 26 * Shoda: 22 - 26 * Ohishi: * Fujii: * Tanaka: * Kozu (ICRR): 22 - 26 * Arai (ICRR): 22 - 26 == Next meeting == On 2018/1/19(Fri)