Agenda/Minutes of the VIS Meeting on 2018/2/9

2018/2/9 13:30 -

Participants:

Progress report

Schedule Chart

Type-A : (PDF/MPP)

Type-B: (PDF,MPP)

  • Type-A:
  • Type-B:

Type-A (Takahashi)

Past week report

[X-front]

  • The delivery of the maraging rod was deley. We didn't go to hunging by the short rod.
  • Attached magnets to the primary coils and made interconnect cables.
  • Installed the protection net into the cross tube.
  • Opened the top chamber.
  • Installed the frame lock.
  • Attached the corn bellows onto the bottom of top chamber.
  • Assembling the side stoppers for SFs.
  • The optimal load of BF (190kg) is not acceptable for the cryo-payload. Designing an additional FR.

[X-end]

  • Attached the additional vacuum gauge to the top chamber. The pressure was 0.16Pa.
  • Checked the connection for LVDT on the F0-BF.

[Y-end]

  • The position of IP was corrected so that the torsion mode frequency can be the lowest.
  • Started the cool down of EYC cryostat on 7th.

[Broken blades]

  • Franco reported about the sample of broken blades. The sample has two different zones.
  • Checked dimensions of some blades. The width was the same, but the thickness was different.
  • Dismounted the blade for SRM from the arc jig.
  • Nikhef can investigate the broken blade too.
  • No information from the maker.
  • Asking the companies about the optimal thickness as material for new blades.

Plan for coming weeks

  • Hung the DP by the short rod.
  • Attached the additional FR and tune the BF again.

Type B (Mark)

Past week report

Plan for coming weeks

Type-Bp (Shoda)

Past week report

Plan for coming weeks

OMMT & OSTM (Ohishi)

Past week report

  • Ordered 4/12 custom-made small bellows for vertical vibration isolation.
  • Some drawings of the hanging jig parts were not updated.
    • need to reorder some mechanical parts.

Plan for coming weeks

  • OSEM test

Watchdog system (Tanaka)

Past week report

  • Preparation for assembly of mass products.-->Ongoing.

  • Adjustment and approval to vendors(Implementation adjustments and approvals for circuit boards.)-->Ongoing.

    • The scheduled delivery date is 22th Feb(final).-->Adjusting.

Plan for coming weeks

  • Preparation for assembly of mass products.
  • Adjustment and approval to vendors(Implementation adjustments and approvals for circuit boards.)

Other site works

  • Feb 18: Black out of the Mozumi buildings
  • 2/26 - 3/9 Construction of the walls to isolate the arms better (for cleanliness)
  • 3/12 - 3/16 Installation of the control systems for the large GVs

Safety

  • Incidents:
  • Foreseen risks
    • Type-A:
    • Type-B:
    • Type-Bp:

Discussion

  • Next FY budget

Travel Plans

  • Travel (Week of 2/12):
    • Takahashi:
    • Okutomi:
    • Sato:
    • Ishizaki:
    • Mark:
    • Fabian:
    • Hirata:
    • Enzo:
    • Shoda:
    • Ohishi:
    • Fujii:
    • Tanaka:
    • Kozu (ICRR):
    • Arai (ICRR):
  • Travel (Week of 2/19):
    • Takahashi:
    • Okutomi:
    • Sato:
    • Ishizaki:
    • Mark:
    • Fabian:
    • Hirata:
    • Enzo:
    • Shoda:
    • Ohishi:
    • Fujii:
    • Tanaka:
    • Kozu (ICRR):
    • Arai (ICRR):

Next meeting

On 2018/2/16(Fri)