= Agenda/Minutes of the VIS Meeting on 2018/2/9 = 2018/2/9 13:30 - 15:00 Participants: Mark, Hirata, Fabian, Izhizaki, Aso, Takahashi, Ohishi, Shoda, Tanaka, Sato, Okutomi, Akutsu == Progress report == === Schedule Chart === Type-A : ([[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7320|PDF/MPP]]) Type-B: ([[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7779|PDF/MPP]]) === Type-A (Takahashi) === ==== Past week report ==== [X-front] * The delivery of the maraging rod was deley. We didn't go to hunging by the short rod. * Attached magnets to the primary coils and made interconnect cables. * Installed the protection net into the cross tube. * Opened the top chamber. * Installed the frame lock. * Attached the corn bellows onto the bottom of top chamber. * Assembling the side stoppers for SFs. * The optimal load of BF (190kg) is not acceptable for the cryo-payload. Designing an additional FR. [X-end] * Attached the additional vacuum gauge to the top chamber. The pressure was 0.16Pa. * Checked the connection for LVDT on the F0-BF. [Y-end] * The position of IP was corrected so that the torsion mode frequency can be the lowest. * Started the cool down of EYC cryostat on 7th. [Broken blades] * Franco reported about the sample of broken blades. The sample has two different zones. * Checked dimensions of some blades. The width was the same, but the thickness was different. * Dismounted the blade for SRM from the arc jig. * Nikhef can investigate the broken blade too. * No information from the maker. * Asking the companies about the optimal thickness as material for new blades. ==== Plan for coming weeks ==== * Hung the DP by the short rod. * Attached the additional FR and tune the BF again. === Type B (Mark) === ==== Report for week of 2/5 ==== * Mark made two sets of in-air pico splitter cables (each with a triple for IM and a double for BF) for SR2 and SR3. * Fabian, Hirata-san and Kozu-kun worked on cabling and testing the IM pitch/roll/yaw picos, the BF FR and the BF LVDT. The LVDT connections were initially unreliable and Hirata-san had to redo the pins on the coil wires. * Fabian installed ballast masses in the BF. * Mark worked on schedule. * Mark did inventory of the stepper motor drivers (many were not accounted for on the wiki and/or JGWDoc and one is missing) and reserved two for SR3. * We emptied out the external cleanroom in preparation for installing SS sheet. ==== Plan for week of 2/13 ==== * No work Monday (建国記念の日の振替休日) * Enzo on vacation * Hirata-san at Mitaka Tue (self-evaluation interview). * Shoda-san at Mitaka. * All others at Kamioka. * - * Build IRM around IM. * Cable/test/adjust IM OSEMs. * Do TFs from IM OSEMs to IM OSEMs, OL pitch/yaw. * Send OSEM parts back to Mitaka so that Shoda-san can assemble them in Mitaka. ==== Plan for week of 2/19 ==== * Enzo back from Tuesday. * Shoda-san at Mitaka. * Hirata-san at Mitaka Mon+Tue (to receive and wash parts). * All others at Kamioka. * - * Lift BF/... section and check total mass and balance. * Cable and test BF picos. * Add section of SS up to SF ring. * Bring in SF. * Hook BF/... section. * Route cables up to under SF. * Check/adjust total mass of BF/... section. ==== Plan for week of 2/26 ==== * Shoda-san at Mitaka. * - * Add Cu segments to SF cap. * Lift SF/... section and check total mass and balance. ==== Vacation Info ==== * Enzo 1/30-2/19. * Fabian 4/2-4/27 vacation (then gone). === Type-Bp (Shoda) === ==== Past week report ==== * Simon and Arai-kun have set up length Oplev for PRM. ==== Plan for coming weeks ==== * Arai-kin, Miyo-kun, and Ohishi-san(?) will close the tank of PRM in order to release SF GAS. === OMMT & OSTM (Ohishi) === ==== Past week report ==== * Ordered 4 custom-made small bellows for vertical vibration isolation. * Some drawings of the hanging jig parts were not updated. need to reorder some mechanical parts. ==== Plan for coming weeks ==== * OSEM test === Watchdog system (Tanaka) === ==== Past week report ==== *Preparation for assembly of mass products.-->Ongoing. *Adjustment and approval to vendors(Implementation adjustments and approvals for circuit boards.)-->Ongoing. *The scheduled delivery date is 22th Feb(final).-->Adjusting. ==== Plan for coming weeks ==== *Preparation for assembly of mass products. *Adjustment and approval to vendors(Implementation adjustments and approvals for circuit boards.) === Other site works === * Feb 18: Black out of the Mozumi buildings * 2/26 - 3/9 Construction of the walls to isolate the arms better (for cleanliness) * 3/12 - 3/16 Installation of the control systems for the large GVs === Safety === * Incidents: no incident * Foreseen risks * Type-A: Crane works * Type-B: No crane work foreseen * Type-Bp: Crane works == Discussion == * Next FY budget * OMMT+OSTM: 14,000KJPY * TF(SR, BS, Type-A) replacement blades: 5,000KJPY * TF Yaw fishing rod modification: 300KJPY * Type-A fishing rod CuBe blades: 100KJPY * Mirror disassembly jig for BS: 300KJPY * Damper ring for SR: 4,000KJPY (2 sets) * SR ballast masses: 1,500KJPY * In-Vacuum Cable Assembly: 400KJPY * ETM PI Geophones: 3,000KJPY (6sets including pods) * Maraging rods: 2MJPY (For Type-A and B SF Damper rings. 12 rods) * Feedthrough: 3MJPY (11 more need to be purchased.) == Travel Plans == * Travel (Week of 2/12): * Takahashi: 13-16 * Okutomi: 13-16 * Sato: 13-16 * Ishizaki: 13-16 * Mark: 13-16 * Fabian: 13-16 * Hirata: 14-16 * Enzo: * Shoda: * Ohishi: * Fujii: * Tanaka: * Kozu (ICRR): 13-16 * Arai (ICRR): 13-16 * Travel (Week of 2/19): * Takahashi: 19 - 23 * Okutomi: 19 - 23 * Sato: 19 - 23 * Ishizaki: 19 - 23 * Mark: 19 - 23 * Fabian: 19 - 23 * Hirata: 21 - 23 * Enzo: 20 - 23 * Shoda: * Ohishi: * Fujii: * Tanaka: * Kozu (ICRR): 19 - 23 * Arai (ICRR): == Next meeting == On 2018/2/16(Fri)