*Preparation for assembly of mass products.-->Ongoing. *Adjustment and approval to vendors(Implementation adjustments and approvals for circuit boards.)-->Ongoing. |
|
Line 32: | Line 37: |
*Preparation for assembly of mass products. *Adjustment and approval to vendors(Implementation adjustments and approvals for circuit boards.) |
Agenda/Minutes of the VIS Meeting on 2018/2/16
2018/2/16 13:30 -
Participants:
Progress report
Schedule Chart
Type-A : (PDF/MPP)
Type-B: (PDF/MPP)
Type-A (Takahashi)
Past week report
Plan for coming weeks
Type B (Mark)
Past week report
Plan for coming weeks
Type-Bp (Shoda)
Past week report
Plan for coming weeks
OMMT & OSTM (Ohishi)
Past week report
Plan for coming weeks
Watchdog system (Tanaka)
Past week report
Preparation for assembly of mass products.-->Ongoing.
Adjustment and approval to vendors(Implementation adjustments and approvals for circuit boards.)-->Ongoing.
Plan for coming weeks
- Preparation for assembly of mass products.
- Adjustment and approval to vendors(Implementation adjustments and approvals for circuit boards.)
Other site works
- Feb 18: Black out of the Mozumi buildings
- 2/21 : Monthly crane inspection 11:30 - 12:30
- 2/26 - 3/9 Construction of the walls to isolate the arms better (for cleanliness)
- 3/12 - 3/16 Installation of the control systems for the large GVs
Safety
- Incidents:
- Foreseen risks
- Type-A:
- Type-B:
- Type-Bp:
Discussion
- Analog electronics management
- Mechanical update history
Travel Plans
- Travel (Week of 2/19):
- Takahashi:
- Okutomi:
- Sato:
- Ishizaki:
- Mark:
- Fabian:
- Hirata:
- Enzo:
- Shoda:
- Ohishi:
- Fujii:
- Tanaka:
- Kozu (ICRR):
- Arai (ICRR):
- Travel (Week of 2/26):
- Takahashi:
- Okutomi:
- Sato:
- Ishizaki:
- Mark:
- Fabian:
- Hirata:
- Enzo:
- Shoda:
- Ohishi:
- Fujii:
- Tanaka:
- Kozu (ICRR):
- Arai (ICRR):
Next meeting
On 2018/2/23(Fri)