= Agenda/Minutes of the VIS Meeting on 2018/2/16 = 2018/2/23 13:30 - Participants: == Progress report == === Schedule Chart === Type-A : ([[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7320|PDF/MPP]]) Type-B: ([[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7779|PDF/MPP]]) === Type-A (Takahashi) === ==== Past week report ==== [X-front] * Attached the additional FR blade to the BF. * Needed some try and errors due to some problems (low Q, FR range, height of blade). * Tuned the BF again. Optimal load was 197.1kg at 0.31Hz. The FR range was 7.5mm. * Closed the cap of BF. * Extended the EQ stop to the F3 stage. * Lifted down the DP into the corrugate tube. * Set the F3 onto the end plate. maraging wire was hooked to the receptacles. * Tuned the F3 to 0.31Hz initially. * The optimal load was changed by closing the cap and hunging the F3. * Finally the frequency was 0.27Hz reducing the weight by 0.4kg. * Checked the range of FR in F3. It was 13.5mm. * Calibrated the LVDT in F3. * Started cabling between the BF and the F3. ==== Plan for coming weeks ==== [Next week] * Finish the cabling between the BF and the F3. * Lift down the BF into the corrugate tube. * Go to the F2 stage. [Week of March 5] * Vent the EXV chamber on 5th. * Remove the IXV DP on 6th. * Insert the maraging wire for Cryo-payload with cables. === Type B (Mark) === ==== Report for week of 2/19 ==== * We did TFs from the IM OSEMs. * We secured the cables inside the BF, added the cap and anchored the cables from below the BF to the cap. * We lifted the BF/... section with the load gauge adapter and measured the weight, which was about as expected. * Based on the measured weight, Fabian prepared an 800 g set of masses for the top of the BF. * We added the AF crossbars and the section of the SS below the SF and craned in the SF. * We installed the SF-BF rod and flying saucer and suspended the BF/... section. With the 800 g placed temporarily on the BF, the SF keystone floated at about mid-range. ==== Plan for week of 2/26 ==== * Shoda-san at Mitaka. * - * Enzo at Mitaka Mon 2/26. * '''Remove LBB temporary ballast masses from BS chamber.''' * Route cables up to under SF. * Check/adjust total mass and balance of BF/... section, especially IM OSEMs. * Cable and calibrate SF LVDT. * Add Cu segments to SF cap. * Install cap. * Lift SF/... section and check total mass and balance. ==== Plan for week of 3/5 ==== * Shoda-san at Mitaka. * Hirata-san vacation Mon 3/5, then Kamioka * Others at Kamioka. * - * Get SRM tank mushroom section installed (Hirata-san, Kimura-san) * SR3 rack setup. * Other tasks TBD. ==== Plan for week of 3/12 ==== * Shoda-san at Mitaka. * Mark at ASJ (Chiba) Fri 3/16. * Hirata-san vacation Mon 3/5, then Kamioka ==== Plan for week of 3/19 ==== * Mark at LVC meeting * Shoda-san, Fabian at Mitaka ==== Plan for week of 3/26 ==== * Mark vacation. * Others ??? ==== To-Do Lists, Schedule ==== * [[KAGRA/Subgroups/VIS/TypeB/March2018]] * [[KAGRA/Subgroups/VIS/TypeB/April2018]] * [[KAGRA/Subgroups/VIS/TypeB/ToDoBS]] * [[KAGRA/Subgroups/VIS/TypeB/ToDoSR]] * [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7779|JGW-L1807779-v1 Type B Schedule (SR)]] ==== Vacation Info ==== * Enzo Mitaka day 2/26 * Hirata-san vacation 3/5 * Hirata-san vacation Mon 3/5 * Fabian 3/26-4/27 vacation (then gone). === Type-Bp (Shoda) === ==== Past week report ==== ==== Plan for coming weeks ==== === OMMT & OSTM (Ohishi) === ==== Past week report ==== *OSEM test *Removed a magnet from OSEM and measured response. It seemed that PD or LED inside OSEM has weak magnetic feature. ==== Plan for coming weeks ==== === Watchdog system (Tanaka) === ==== Past week report ==== *Preparation for assembly of mass products.-->Ongoing. *Adjustment and approval to vendors(Implementation adjustments and approvals for circuit boards.)--> *There is no delivery.-->Contacting the vendor. ==== Plan for coming weeks ==== *Preparation for assembly of mass products. *Adjustment and approval to vendors(Implementation adjustments and approvals for circuit boards.) === Other site works === * 2/26 - 3/9 Construction of the walls to isolate the arms better (for cleanliness) * 3/12 - 3/16 Installation of the control systems for the large GVs * 3/12 - Center area: preparation for pump down: connecting ducts. === Safety === * Incidents: * Foreseen risks * Type-A: * Type-B: * Type-Bp: == Discussion == * Center area pump down * PR2/3 height adjustment == Travel Plans == * Travel (Week of 2/26): * Takahashi: 26 -2 * Okutomi: 26 -2 * Sato: 26 -1 * Ishizaki: 26 -1 * Mark: 26 -2 * Fabian: 26 -2 * Hirata:26 -2 * Enzo:27 -2 * Shoda: * Ohishi: * Fujii: * Tanaka: * Kozu (ICRR): 26 -2 * Arai (ICRR): * Travel (Week of 3/5): * Takahashi: 5 - 9 * Okutomi: 5 - 9 * Sato: 5 - 9 * Ishizaki: 5 - 9 * Mark: 5 - 9 * Fabian: 5 - 9 * Hirata: 6 - 9 * Enzo: 5 - 9 * Shoda: * Ohishi: * Fujii: * Tanaka: * Kozu (ICRR): 5 - 9 * Arai (ICRR): == Next meeting == On 2018/3/2(Fri) VIS Meeting in Mitaka: 3/16