= Agenda/Minutes of the VIS Meeting on 2018/3/2 = 2018/3/2 13:30 - 15:40 Participants: Fabian, Takahashi, Aso, Tanaka, Enzo, Okutomi, Hirata, Mark, Shoda, Ishizaki == Progress report == === Schedule Chart === Type-A : ([[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7320|PDF/MPP]]) Type-B: ([[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7779|PDF/MPP]]) === Type-A (Takahashi) === ==== Past week report ==== [X-front] * Finished the cabling between the BF and F3. * Tuned the F3 again with hanging the F3 by crane. * Final optimal load was additionally 1.2kg at 0.25Hz. * Removed the primary coils for the BF damper. * Checked cable connections and repaired some disconnections. * Started the installation of F2. Assembled the FR in the F2. ==== Plan for coming weeks ==== [X-front] * Measure the transfer functions of the BF and the F3. * Lift down the BF into the corrugate tube. * Extend the EQ stop for the F2. [X-end] * Vent the chamber on 5th. * Remove the DP on 6th. * Install the maraging wire for Cryo-payload with cables on 7th. === Type B (Mark) === ==== Report for week of 2/26 ==== * We routed all the cables from the BF level up via the flying saucer to the SF. * Hirata-san tried filing the SF cap to improve the fit, but without much success. * Hirata-san installed the Cu segments and cable clamps on the SF cap and the SF LVDT and FR cables. * We cabled and tested the BF cap picos and the SF LVDT and FR. (The LVDT still needs a full calibration.) * We worked on recovering the IM OSEM alignment. ==== Plan for week of 3/5 ==== * Shoda-san at Mitaka. * Hirata-san vacation Mon 3/5, then Kamioka * Fabian Mitaka Mon-Tue (COMSOL training), Kamioka Wed-Fri. * Others at Kamioka. * - * '''Remove LBB temporary ballast masses from BS chamber.''' * Finish recovering IM OSEM alignment. * Calibrate SF LVDT. * Lift SF/... section and check total mass and balance. * Get SRM tank mushroom section installed (Hirata-san, Kimura-san) * Set up for rebuilding of two BFs. ==== Plan for week of 3/12 ==== * Shoda-san at Mitaka. * Mark at ASJ (Chiba) Fri, then Mitaka. * Hirata-san vacation Mon 3/5; Kamioka Tue-Thu; Mitaka Fri * Others Kamioka Mon-Thu * Install boxes in SR3 and SRM racks. * Lay SR3 in-air cabling. * Continue rebuild of BFs. ==== Plan for week of 3/19 ==== * Mark at LVC meeting * All others at Mitaka * Make two sets of IM OSEMs * Make last in-air pico adapter cable * Make three in-air stepper splitter cables for SR2, SR3 and SRM. * Set up Dummy BS prism removal. ==== Plan for week of 3/26 ==== * Mark vacation. * Shoda-san at Mitaka * Others at Kamioka * -- * F0 Prototype Blade Test * Characterize blades. * Choose best set of three. * Remove cracked blades from filter in SRM area. * Set up test weights in SRM area, first floor. * Remove floor panel in SRM area, second floor. * Install chosen blades. * Measure load capacity. ==== To-Do Lists, Schedule ==== * [[KAGRA/Subgroups/VIS/TypeB/March2018]] * [[KAGRA/Subgroups/VIS/TypeB/April2018]] * [[KAGRA/Subgroups/VIS/TypeB/ToDoBS]] * [[KAGRA/Subgroups/VIS/TypeB/ToDoSR]] * [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7779|JGW-L1807779-v1 Type B Schedule (SR)]] ==== Vacation Info ==== * Mark at LVC, then vacation, 3/18 (Sun) - 4/1 (Sun) * Hirata-san vacation, Mon 3/5. * Fabian vacation, 3/26-4/27 (then gone). === Type-Bp (Shoda) === ==== Past week report ==== * Takahashi-san, Aso-san, Ohishi-san, and Miyo-kun checked the suspension height. But the height was not much changed. So SF weight was not changed. I checked the LVDT trend since the installation. There are some jumps after data taking errors, including blackouts. Details will be uploaded to klog later. * I prepared IP stepping motor med scripts. Actuation check is required. * PRM guardian has an error that I could not solve. ==== Plan for coming weeks ==== === OMMT & OSTM (Ohishi) === ==== Past week report ==== ==== Plan for coming weeks ==== === Watchdog system (Tanaka) === ==== Past week report ==== *Preparation for assembly of mass products.-->Ongoing. *Adjustment and approval to vendors(Implementation adjustments and approvals for circuit boards.)--> *Delivered( 5 of 6 substrates and Cables(assembled)). *There are two casings yet(Adjusting with vendor) *Operation test of the initial product is completed. And I ordered the production of the residual mass-produced products.-->Pending delivery. ==== Plan for coming weeks ==== *Preparation for assembly of mass products.--> *Programming and Unit Testing(59 Items) *Other necessary preparations. *Adjustment and approval to vendors(Negotiating to guarantee machining delay of cases). === Other site works === * 2/26 - 3/9 Construction of the walls to isolate the arms better (for cleanliness) *3/8 or 3/9 no car in the access tunnel * 3/12 - 3/16 Installation of the control systems for the large GVs * 3/12 - Center area: preparation for pump down: connecting ducts. === Safety === * Incidents: no incident * Foreseen risks * Type-A: Crane work * Type-B: Crane work, working with springs * Type-Bp: == Discussion == === Center area pump down === ==== Vacuum flange status ==== * BS * Top flange: O-ring inside, but covered with mending tapes (not vacuum compatible) * Small service flanges in the bottom section near the top flange (2 of them): Opened once. Not tightened. Maybe no O-ring. * Feed through flanges: Metal gaskets inside. Not tightened. * A blank flange in place of a feed through flange: Maybe no O-ring. Not tightened. * PRM * Top flange: No O-ring * Feedthrough flanges: Metal gaskets inside. Not tightened. * PR2/PR3 * Top flange: O-ring inside. Not tightened. To be tightened by Futaba in the week of Mar. 5th. * Feedthrough flanges: Metal gaskets inside. Not tightened. ==== Other preparations ==== * Securing cables * D-sub connectors on the PR chambers are not fixed by screws * Type-B team has about 150 pairs of the screws * Type-B team will put screws for PR2 chamber in the next week * Need to assign someone for PR3/M * OpLev monitoring * Aso will work with Shoda to implement Guardian alert system to send notifications when OpLev is kicked. * PRM guardian is not running now. Aso will talk with Kokeyama and Yamamoto. * Drift monitoring of the suspensions during pump down * A strip tool should be prepared to show the drift trend * Wiping inside the chambers * PR2 and BS: Type-B team * PRM and PR3: Ask someone === Phase 1 operation measurements === * We need to clarify: * Minimum success criteria for each measurement * Who will do the task * Type-A transfer function measurements * Main people: Okutomi, Miyamoto, Fujii(?) * Criteria: Okutomi will discuss with Miyamoto * Bs transfer function measurements * Main people: Mark, Enzo * Criteria: Mark will make a list of transfer functions to be measured == Travel Plans == * Travel (Week of 3/5): * Takahashi: 5-9 * Okutomi: 5-8 * Sato: 5-9 * Ishizaki: 5-9 * Mark: 5-9 * Fabian: 7-9 * Hirata: 6-9 * Enzo: 5-9 * Shoda: * Ohishi: * Fujii: * Tanaka: * Kozu (ICRR): 5-9 * Arai (ICRR): * Travel (Week of 3/12): * Takahashi: 13 - 15 * Okutomi: 12 - 15 * Sato: 12 - 15 * Ishizaki: 12 - 15 * Mark: 12 - 15 * Fabian: 12 - 15 * Hirata: 12 - 15 * Enzo: * Shoda: * Ohishi: * Fujii: * Tanaka: * Kozu (ICRR): 12 - 15 * Arai (ICRR): == Next meeting == On 2018/3/9(Fri) VIS Meeting in Mitaka: 3/16