Line 56: Line 56:
 *Preparation for assembly of mass products.-->
    *Programming and Unit Testing(30 Items).-->30/30 Items completed.
   
 *I started to assemble the apparatus.-->Completed.

 *Final system test -->Completed.

 *I plan to ship to Kamioka on 22nd(For equipments installation from 26th to the week).-->Completed.

 *Other necessary preparations.
Line 57: Line 68:

 *Business trip plan
    *March 25(Toyama),26th-29th(Kamioka),30th(Preliminary day Toyama->Tokyo)
    
 *Installation place-->PRM,PR3,PR2,BS,SR2(However,only to install. Launch is done on another occasion.)

Agenda/Minutes of the VIS Meeting on 2018/3/23

2018/3/23 13:30 -

Participants:

Progress report

Schedule Chart

Type-A : (PDF/MPP)

Type-B: (PDF/MPP)

Type-A (Takahashi)

Past week report

[X-front]

  • Installed the F1 into the clean booth. Opened the cap of F1. The fitting was very tight.
  • Embedded the FR. Prepared for the wire with the small hexagons.
  • Lifted down the EQ stop. The end plate for F2 was sit on the frame lock.
  • Extended the EQ stop to the F1 stage.

[X-end]

  • Removed the yoke of vertical actuator in the TF. Pushed down the keystone of TF.
  • Connected the cables from the cryo-payload (CP) to the BF.
  • Released the BF. Adjusted the position of EQ stop anchor.
  • The CP was installed into the cryostat. The maraging wire was hooked to the CP.
  • Released the CP. The height of mirror was lower than the design one by 8mm.
  • Released the keystone of TF. Set the height of BF to 78mm.

Plan for coming weeks

[X-front]

  • Mount the F1 on the EQ stop and hang the F2 from the F1.
  • Tune the F1.
  • Cable between the F2 and the F1.

[X-end]

  • Check the cable connections.
  • Adjust the weight of BF and TF.
  • Close the chambers.

Type B (Mark)

Past week report

Plan for coming weeks

Type-Bp (Shoda)

Past week report

Plan for coming weeks

OMMT & OSTM (Ohishi)

Past week report

Plan for coming weeks

Watchdog system (Tanaka)

Past week report

  • Preparation for assembly of mass products.-->

    • Programming and Unit Testing(30 Items).-->30/30 Items completed.

  • I started to assemble the apparatus.-->Completed.

  • Final system test -->Completed.

  • I plan to ship to Kamioka on 22nd(For equipments installation from 26th to the week).-->Completed.

  • Other necessary preparations.

Plan for coming weeks

  • Business trip plan
    • March 25(Toyama),26th-29th(Kamioka),30th(Preliminary day Toyama->Tokyo)

  • Installation place-->PRM,PR3,PR2,BS,SR2(However,only to install. Launch is done on another occasion.)

Other site works

Safety

  • Incidents:
  • Foreseen risks
    • Type-A: Crane work
    • Type-B:
    • Type-Bp:

Discussion

Travel Plans

  • Travel (Week of 3/26):
    • Takahashi: 3/26-30
    • Okutomi:
    • Sato: 3/26-30
    • Ishizaki: 3/26-30
    • Mark:
    • Fabian:
    • Hirata:
    • Enzo:
    • Shoda:
    • Ohishi:
    • Fujii:
    • Tanioka:
    • Tanaka:
    • Kozu (ICRR):
    • Arai (ICRR):
  • Travel (Week of 4/2):
    • Takahashi: 4/2-6
    • Okutomi:
    • Sato: 4/2-6
    • Ishizaki: 4/2-6
    • Mark:
    • Fabian:
    • Hirata:
    • Enzo:
    • Shoda:
    • Ohishi:
    • Fujii:
    • Tanioka:
    • Tanaka:
    • Kozu (ICRR):
    • Arai (ICRR):

Next meeting

On 2018/3/30(Fri)

KAGRA/Subgroups/VIS/VISMinutes20180323 (last edited 2018-03-23 14:33:47 by YoichiAso)