= Agenda/Minutes of the VIS Meeting on 2018/3/23 = 2018/3/23 13:30 - 14:10 Participants: Tanioka, Fujii, Aso, Eleonora, Mark, Hirata, Tanaka, Sato, Enzo, Shoda == Progress report == === Schedule Chart === Type-A : ([[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7320|PDF/MPP]]) Type-B: ([[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7779|PDF/MPP]]) === Type-A (Takahashi) === ==== Past week report ==== [X-front] * Installed the F1 into the clean booth. Opened the cap of F1. The fitting was very tight. * Embedded the FR. Prepared for the wire with the small hexagons. * Lifted down the EQ stop. The end plate for F2 was sit on the frame lock. * Extended the EQ stop to the F1 stage. [X-end] * Removed the yoke of vertical actuator in the TF. Pushed down the keystone of TF. * Connected the cables from the cryo-payload (CP) to the BF. * Released the BF. Adjusted the position of EQ stop anchor. * The CP was installed into the cryostat. The maraging wire was hooked to the CP. * Released the CP. The height of mirror was lower than the design one by 8mm. * Released the keystone of TF. Set the height of BF to 78mm. ==== Plan for coming weeks ==== [X-front] * Mount the F1 on the EQ stop and hang the F2 from the F1. * Tune the F1. * Cable between the F2 and the F1. [X-end] * Check the cable connections. * Adjust the weight of BF and TF. * Close the chambers. === Type B (Mark) === ==== Report for week of 3/19 ==== * Fujii-kun successfully assembled and tested a geophone pod (klogs 4492, 4508). * Hirata-san set up the dummy BS to soak off the sapphire prisms (ongoing). * Shoda-san, Hirata-san and Enzo finished the assembly of 12 OSEMs. We still need to measure the maximum output (ongoing). * We will send the OSEMs to Kamioka today. * Enzo made 2 in-air picomotor cable. ==== Plan for week of 3/26 ==== * Tanioka-kun joins. * Mark vacation. * Shoda-san at Mitaka * Others at Kamioka * -- * Lay SR3 in-air cabling (Enzo++). * Finish tuning of BFs (Hirata-san++). * SF check (Hirata-san++). * Check load capacity. * Check fit of caps. * Add cable clamps to bases. * Add cable clamps and Cu segments to caps (only if they fit well). * Cable LVDTs and steppers. ==== Plan for week of 4/2 ==== * Mark at Mitaka Mon, Kamioka from Tue. * Shoda-san at Mitaka * Others at Kamioka * -- * Glue SR3 (if available) * Build 2xIM, 2xIRM (if parts available - due 3/30) ==== Plan for week of 4/9 ==== * Shoda-san at Mitaka * Others at Kamioka * -- * Finish IMs and IRMs * Build 1xRM ==== Plan for week of 4/16 ==== * Start SR3 Hang? ==== Plan for week of 4/23 ==== * F0 blade prototype test ==== Plan for week of 4/30 ==== * Golden Week! ==== To-Do Lists, Schedule ==== * [[KAGRA/Subgroups/VIS/TypeB/March2018]] * [[KAGRA/Subgroups/VIS/TypeB/April2018]] * [[KAGRA/Subgroups/VIS/TypeB/ToDoBS]] * [[KAGRA/Subgroups/VIS/TypeB/ToDoSR]] * [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7779|JGW-L1807779-v1 Type B Schedule (SR)]] ==== Control Issues ==== * BS * V3 OSEM does not seem to be working properly. * Enzo will check the cables and the satellite box if they are working fine. * SR2 * BIO is not working properly. WD reset pulses are not working. And some TEST/COIL switch pulse work strangely. More investigation required. * Enzo will check the BIO with the LED indicator board. ==== Vacation Info ==== * Mark at LVC, then vacation, 3/18 (Sun) - 4/1 (Sun) * Fabian vacation, 3/26-4/27 (then gone). === Type-Bp (Shoda) === ==== Past week report ==== ==== Plan for coming weeks ==== === OMMT & OSTM (Ohishi) === ==== Past week report ==== ==== Plan for coming weeks ==== === Watchdog system (Tanaka) === ==== Past week report ==== *Preparation for assembly of mass products.--> *Programming and Unit Testing(30 Items).-->30/30 Items completed. *I started to assemble the apparatus.-->Completed. *Final system test -->Completed. *I plan to ship to Kamioka on 22nd(For equipments installation from 26th to the week).-->Completed. *Other necessary preparations. ==== Plan for coming weeks ==== *Business trip plan *March 25(Toyama),26th-29th(Kamioka),30th(Preliminary day Toyama->Tokyo) *Installation place-->PRM,PR3,PR2,BS,SR2(However,only to install. Launch is done on another occasion.) === Other site works === === Safety === * Incidents: no incidet * Safety bars around the SR2 assembly frame were set up by Furuta-san. * Foreseen risks * Type-A: Crane work * Type-B: Crane work, working with springs * Type-Bp: == Discussion == == Travel Plans == * Travel (Week of 3/26): * Takahashi: 3/26-30 * Okutomi: * Sato: 3/26-30 * Ishizaki: 3/26-30 * Mark: * Hirata: 26-30 * Enzo: 26-30 * Shoda: * Ohishi: * Fujii: 26-30 * Tanioka: 27-30 * Tanaka: 26-29 * Kozu (ICRR): 26-30 * Arai (ICRR): * Travel (Week of 4/2): * Takahashi: 4/2-6 * Okutomi: * Sato: 4/2-6 * Ishizaki: 4/2-6 * Mark: 4/3-6 * Hirata: 4/3-6 * Enzo: 4/2-5 * Shoda: * Ohishi: * Fujii: ? * Tanioka: 4/2-6 * Tanaka: * Kozu (ICRR): 4/2-6? * Arai (ICRR): == Next meeting == On 2018/3/30(Fri)