Differences between revisions 1 and 21 (spanning 20 versions)
Revision 1 as of 2018-04-11 13:09:06
Size: 1494
Editor: YoichiAso
Comment:
Revision 21 as of 2018-04-13 17:17:45
Size: 6214
Editor: YoichiAso
Comment:
Deletions are marked like this. Additions are marked like this.
Line 3: Line 3:
2018/4/13 13:30 - 2018/4/13 13:30 - 15:20
Line 5: Line 5:
Participants: Participants: Mark, Takahashi, Ishizaki, Aso, Hirata, Ohishi, Sato, Simon, Shoda, Tanaka, Enzo, Fujii, Okutomi, Tanioka
Line 15: Line 15:

[X-front]
  * Set the bridge frame on the footholds.
  * Installed the IP and TF into the clean booth.
  * Combined the IP and the TF.
  * Dismounted the GAS blades from the TF.
  * Assembled the FR on the TF.
  * Assembled the new designed yaw actuator on the TF. Not completed.
  * Prepared the damper ring with magnets for the F1.
  * Cabled around the TF.
  * Repairing the side stoppers for the IY EQ stop.
Line 17: Line 29:
[X-front]
  * Mount the GAS blades on the TF.
  * Set the PI on the bridge frame.
  * Tune the TF.
  * Cable between the F1 and PI.
Line 18: Line 36:
==== Past week report ====
==== Plan for coming weeks ====
==== Report for week of 4/9 ====
 * Mark glued prisms and magnet/standoff assemblies on the SR3. The SR3 needed to be raised in the box by 0.7 mm to make the prisms go on at the right height, which was done using M4 washers under the PEEK feet.
 * Mark glued ferromagnetic disks on the last 5 IM flags. This completes 2 sets, for SR3 and SRM.
 * Mark configured two pico motor drivers ordered by Takahashi-san as SR3-IM and SRM-BF.
 * Enzo and Kozu-kun finished preparing and calibrating the SF and BF for SR3 and almost entirely finished with those for SRM.
 * Hirata-san worked on building two IMs for SR3 and SRM. The SR3 one just needs to have flags attached and to be weighed; the SRM needs another few hours work.
 * Shoda-san worked on the design of the metal SRM, on the LBB ballast mass, and on the plans for testing the BS in bKAGRA Phase 1.
Line 21: Line 44:
==== Plan for week of 4/16 ====
 * Shoda-san, Fujii-kun at Mitaka
 * Tanioka-san at Kamioka Tue-Thu
 * Others at Kamioka full week
 * --
 * Move SF and BF for SRM out of the way.
 * Check results of gluing.
 * Build 1xRM
 * Calibrate OSEMs.
 * Start SR3 Hang
  * Reset assembly frame crossbars to correct heights.
  * Center the optical table.
  * Align the assembly frame vertically.
  * Install IM ring and IM.
  * Hang optic.
  * Hang RM.
  * Cable RM OSEMs.

==== Plan for week of 4/23 ====
 * Shoda-san, Tanioka-san at Mitaka
 * Hirata-san at Mitaka Mon, Tue, then Kamioka
 * Mark, Enzo, Fujii-kun, Kozu-kun, Tanioka-kun at Kamioka
 * --
 * Clean parts (cable clamp bases, etc, etc).
 * Observe KAGRA Phase 1 operations, assist if problems arise.
 * Continue SR3 hang.

==== Plan for week of 4/30 ====
  * Golden Week!

==== To-Do Lists, Schedule ====
 * [[KAGRA/Subgroups/VIS/TypeB/March2018]]
 * [[KAGRA/Subgroups/VIS/TypeB/April2018]]
 * [[KAGRA/Subgroups/VIS/TypeB/ToDoBS]]
 * [[KAGRA/Subgroups/VIS/TypeB/ToDoSR]]
 * [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7779|JGW-L1807779-v1 Type B Schedule (SR)]]

==== Vacation Info ====
 * Fabian vacation, 3/26-4/27 (then gone).
Line 27: Line 89:
 * Estimated effect of OSEM magnetism
  *https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/DocDB/ShowDocument?docid=8154
  *If you find any mistake, please let me know.
 * Checked drawings in detail and ordered some minor changes of drawings.
 
 * OMMT mirrors have been delivered to Kashiwa.
  *OMMT1: diameter 99.95mm, thickness 55.58mm(max), wedge 2.45deg
  *OMMT2: diameter 99.97mm, thickness 55.08mm(max), wedge 3.3deg
Line 28: Line 99:
 * Order mechanical parts
 * Design glueing jig for OMMT
Line 36: Line 108:
 * Incidents:  * Incidents: no incident
Line 39: Line 111:
  * Type-A:
  * Type-B:
  * Type-A: Crane work
  * Type-B: Crane work
Line 44: Line 116:
 * Composite SRM design (Shoda)
=== Yaw fishing rod for the top filter ===
  * The redesigned one did not work
  * We need to replace it by mid June
  * Had a discussion after the VIS meeting.
   * Try to fix the stepper motor, relying on the flexible coupling to absorb the on-axis motion.

=== Composite SRM design (Shoda) ===
 * Oplev:
  * Use HR side of the SRM 2-inch mirror, and do not have any mirror on the AR side.
  * The coupling rate from the transverse/vertical motion to the beam angle due to the curvature would be about 4 urad /1 mm mirror motion.
 -> It largely simplifies the design.

  * [A/I] Check whether Oplev bread boards can be fixed at the AR side of the outer frame. (Simon)
  * [A/I] Double check the coupling rate from the transverse/vertical motion to the beam spot due to the curvature. (Aso)

 * Inner duct:
  * Make it wider as much as possible, and insert black-coated pipe.

  * [A/I] Proceed the design of the metal mass and the inner pipe. (Shoda)

 * Mirror holder:
  * Discussion on going.
  * Gluing is preferable if possible, because it is easier to manufacture.
  * Possible problems are:
   * bubbles in glue
   * black-coated surface and glass can be glued?
   * gluing procedure (how to put glue, etc.)

=== LVDT drivers ===
 * Check the current status
  * see [[KAGRA/Subgroups/VIS/OpsManual/LVDT#stocktake]].
 * We probably need to buy more cards
Line 48: Line 152:
  * Takahashi:   * Takahashi: 16 - 20
Line 50: Line 154:
  * Sato:   * Sato: 17 - 20
Line 52: Line 156:
  * Mark:
  * Hirata:
  * Enzo:
  * Mark: 16 - 20
  * Hirata: 16 - 20
  * Enzo: 16 - 20
Line 58: Line 162:
  * Tanioka:   * Tanioka: 17 - 19
Line 60: Line 164:
  * Kozu (ICRR):   * Kozu (ICRR): 16 - 20
Line 65: Line 169:
  * Takahashi:   * Takahashi: 23 - 27
Line 67: Line 171:
  * Sato:   * Sato: 23 - 27
Line 69: Line 173:
  * Mark:
  * Hirata:
  * Enzo:
  * Mark: 23 - 27
  * Hirata: 25 - 27
  * Enzo: 23 - 27
Line 74: Line 178:
  * Fujii:
  * Tanioka:
  * Fujii: 23 - 27
  * Tanioka: 23 - 27
Line 77: Line 181:
  * Kozu (ICRR):   * Kozu (ICRR): 23 - 27

Agenda/Minutes of the VIS Meeting on 2018/4/13

2018/4/13 13:30 - 15:20

Participants: Mark, Takahashi, Ishizaki, Aso, Hirata, Ohishi, Sato, Simon, Shoda, Tanaka, Enzo, Fujii, Okutomi, Tanioka

Progress report

Schedule Chart

Type-A : (PDF/MPP)

Type-B: (PDF/MPP)

Type-A (Takahashi)

Past week report

[X-front]

  • Set the bridge frame on the footholds.
  • Installed the IP and TF into the clean booth.
  • Combined the IP and the TF.
  • Dismounted the GAS blades from the TF.
  • Assembled the FR on the TF.
  • Assembled the new designed yaw actuator on the TF. Not completed.
  • Prepared the damper ring with magnets for the F1.
  • Cabled around the TF.
  • Repairing the side stoppers for the IY EQ stop.

Plan for coming weeks

[X-front]

  • Mount the GAS blades on the TF.
  • Set the PI on the bridge frame.
  • Tune the TF.
  • Cable between the F1 and PI.

Type B (Mark)

Report for week of 4/9

  • Mark glued prisms and magnet/standoff assemblies on the SR3. The SR3 needed to be raised in the box by 0.7 mm to make the prisms go on at the right height, which was done using M4 washers under the PEEK feet.
  • Mark glued ferromagnetic disks on the last 5 IM flags. This completes 2 sets, for SR3 and SRM.
  • Mark configured two pico motor drivers ordered by Takahashi-san as SR3-IM and SRM-BF.
  • Enzo and Kozu-kun finished preparing and calibrating the SF and BF for SR3 and almost entirely finished with those for SRM.
  • Hirata-san worked on building two IMs for SR3 and SRM. The SR3 one just needs to have flags attached and to be weighed; the SRM needs another few hours work.
  • Shoda-san worked on the design of the metal SRM, on the LBB ballast mass, and on the plans for testing the BS in bKAGRA Phase 1.

Plan for week of 4/16

  • Shoda-san, Fujii-kun at Mitaka
  • Tanioka-san at Kamioka Tue-Thu
  • Others at Kamioka full week
  • --
  • Move SF and BF for SRM out of the way.
  • Check results of gluing.
  • Build 1xRM
  • Calibrate OSEMs.
  • Start SR3 Hang
    • Reset assembly frame crossbars to correct heights.
    • Center the optical table.
    • Align the assembly frame vertically.
    • Install IM ring and IM.
    • Hang optic.
    • Hang RM.
    • Cable RM OSEMs.

Plan for week of 4/23

  • Shoda-san, Tanioka-san at Mitaka
  • Hirata-san at Mitaka Mon, Tue, then Kamioka
  • Mark, Enzo, Fujii-kun, Kozu-kun, Tanioka-kun at Kamioka
  • --
  • Clean parts (cable clamp bases, etc, etc).
  • Observe KAGRA Phase 1 operations, assist if problems arise.
  • Continue SR3 hang.

Plan for week of 4/30

  • Golden Week!

To-Do Lists, Schedule

Vacation Info

  • Fabian vacation, 3/26-4/27 (then gone).

Type-Bp (Shoda)

Past week report

Plan for coming weeks

OMMT & OSTM (Ohishi)

Past week report

  • Estimated effect of OSEM magnetism
  • Checked drawings in detail and ordered some minor changes of drawings.
  • OMMT mirrors have been delivered to Kashiwa.
    • OMMT1: diameter 99.95mm, thickness 55.58mm(max), wedge 2.45deg
    • OMMT2: diameter 99.97mm, thickness 55.08mm(max), wedge 3.3deg

Plan for coming weeks

  • Order mechanical parts
  • Design glueing jig for OMMT

Watchdog system (Tanaka)

Past week report

Plan for coming weeks

Other site works

Safety

  • Incidents: no incident
  • Foreseen risks
    • Type-A: Crane work
    • Type-B: Crane work
    • Type-Bp:

Discussion

Yaw fishing rod for the top filter

  • The redesigned one did not work
  • We need to replace it by mid June
  • Had a discussion after the VIS meeting.
    • Try to fix the stepper motor, relying on the flexible coupling to absorb the on-axis motion.

Composite SRM design (Shoda)

  • Oplev:
    • Use HR side of the SRM 2-inch mirror, and do not have any mirror on the AR side.
    • The coupling rate from the transverse/vertical motion to the beam angle due to the curvature would be about 4 urad /1 mm mirror motion.

    -> It largely simplifies the design.

    • [A/I] Check whether Oplev bread boards can be fixed at the AR side of the outer frame. (Simon)
    • [A/I] Double check the coupling rate from the transverse/vertical motion to the beam spot due to the curvature. (Aso)
  • Inner duct:
    • Make it wider as much as possible, and insert black-coated pipe.
    • [A/I] Proceed the design of the metal mass and the inner pipe. (Shoda)
  • Mirror holder:
    • Discussion on going.
    • Gluing is preferable if possible, because it is easier to manufacture.
    • Possible problems are:
      • bubbles in glue
      • black-coated surface and glass can be glued?
      • gluing procedure (how to put glue, etc.)

LVDT drivers

Travel Plans

  • Travel (Week of 4/16):
    • Takahashi: 16 - 20
    • Okutomi:
    • Sato: 17 - 20
    • Ishizaki:
    • Mark: 16 - 20
    • Hirata: 16 - 20
    • Enzo: 16 - 20
    • Shoda:
    • Ohishi:
    • Fujii:
    • Tanioka: 17 - 19
    • Tanaka:
    • Kozu (ICRR): 16 - 20
    • Arai (ICRR):
  • Travel (Week of 4/23):
    • Takahashi: 23 - 27
    • Okutomi:
    • Sato: 23 - 27
    • Ishizaki:
    • Mark: 23 - 27
    • Hirata: 25 - 27
    • Enzo: 23 - 27
    • Shoda:
    • Ohishi:
    • Fujii: 23 - 27
    • Tanioka: 23 - 27
    • Tanaka:
    • Kozu (ICRR): 23 - 27
    • Arai (ICRR):

Next meeting

On 2018/4/20(Fri)

KAGRA/Subgroups/VIS/VISMinutes20180413 (last edited 2018-04-13 17:17:45 by YoichiAso)