Size: 1749
Comment:
|
Size: 5240
Comment:
|
Deletions are marked like this. | Additions are marked like this. |
Line 3: | Line 3: |
2018/4/20 13:30 - | 2018/4/20 13:30 - 15:20 |
Line 5: | Line 5: |
Participants: | Participants: Mark, Shoda, Takahashi, Sato, Aso, Okutomi, Ishizaki, Tanioka, Eleonora, Enzo, Fujii, Hirata, Akutsu, Tanaka |
Line 15: | Line 15: |
[X-front] * Bent and formed six blades to mount on the TF base. * Mounted the blades on the TF base. * Put the damper ring with magnets on the F1. * Mounted the PI on the bridge frame with the maraging wire. * Suspended the filter chain from the TF. Needed load was about 700kg for the TF in spite of target load of 580kg. * Removed one blade and rearranged two blade. The TF could work without additional load. * Suspended the damper ring from the TF base. One hook screw galled. * Cabled between the F1 and the upper small hexagon. * Inserted the wire clamp. * Dismounted the PI and bridge frame. * Checked the cable connections. * Lifted down the F1 into the corrugate tube. The top ring sit on the frame lock. * Installed the PI into the top chamber. |
|
Line 17: | Line 33: |
[X-front] * Cable to the feedthroughs. * Set the ACCs. * Calibrate the LVDTs for the BF damper and the IP. |
|
Line 18: | Line 39: |
==== Past week report ==== ==== Plan for coming weeks ==== |
==== Report for week of 4/9 ==== * We packed away the SRM SF and BF. * After several failed attempts with one secondary prism, Mark finished the SR3 prism/magnet gluing. * Tanioka-kun built two IRMs (less OSEMs). * Enzo built an RM. * Kozu-kun and Enzo calibrated one set of 6 IM OSEMs for SR3. (6 OSEMs for SRM remain to be done.) * Hirata-san aligned the assembly frame, installed the interface bars and IM ring, and installed the IM. * Eleonora and Izumi-san revisited the BS length to tilt coupling, which had degraded, and got it working again. |
Line 21: | Line 48: |
==== Plan for week of 4/23 ==== * Shoda-san at Mitaka. * Hirata-san at Kamioka Mon-Wed, then Mitaka. * Kozu-kun at Kamioka Wed-Fri (but may be working with PEM on Fri). * Others (Mark, Enzo, Tanioka-kun) at Kamioka full week * -- * Continue SR3 Hang * Hang optic. * Hang RM. * Cable RM OSEMs. ==== Plan for week of 4/30 ==== * Shoda-san at Mitaka. * Mark, Enzo at Kamioka Mon-Wed or TBD. * Others having fun doing Golden Week stuff. * -- * Observe KAGRA Phase 1 operations, assist if problems arise. * Do BF TFs. * Continue SR3 hang. ==== To-Do Lists, Schedule ==== * [[KAGRA/Subgroups/VIS/TypeB/March2018]] * [[KAGRA/Subgroups/VIS/TypeB/April2018]] * [[KAGRA/Subgroups/VIS/TypeB/ToDoBS]] * [[KAGRA/Subgroups/VIS/TypeB/ToDoSR]] * [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7779|JGW-L1807779-v1 Type B Schedule (SR)]] ==== Vacation Info ==== * Fabian vacation, 3/26-4/27 (then gone). |
|
Line 29: | Line 85: |
=== Watchdog system (Tanaka) === | === LVDT Driver (Tanaka) === |
Line 36: | Line 92: |
* Incidents: | * Incidents: no incident |
Line 44: | Line 100: |
* Composite SRM design (Shoda) * ETMY tower repair (Takahashi, Okutomi) * Phase 1 Operation Reschedule * LVDT drivers * [[http://gwwiki.icrr.u-tokyo.ac.jp/JGWwiki/KAGRA/Subgroups/VIS/OpsManual/LVDT#stocktake|Staocktake]] * Buy 10 sets * Check the broken boards in Mitaka |
=== Composite SRM design (Shoda) === * After some discussions, a new idea of gluing the HR surface to a PEEK ring emerged. * Shoda-san will elaborate on the idea and report to the relevant people. === ETMY tower repair (Takahashi, Okutomi) === * According to Okutomi-kun's TF measurements, even the F3 stage may be stuck. * We should be able to release the F3 GAS by adjusting the mass on the BF from the cross-tube. * We will try this before O3. * Takahashi-san will make a schedule for the ETMY repair works by the next VIS meeting. === [[https://www.dropbox.com/s/u685czkj8gddd52/Chief180402%E3%80%80Phase1%20after%20experiments.pdf?dl=0|Phase 1 Operation Reschedule]] * Mark, Enzo, Okutomi, Tanioka, Kozu will join the operation. * Shoda-san will join remotely through Skype or something (communication method will be announced by Mark) === LVDT drivers === * [[http://gwwiki.icrr.u-tokyo.ac.jp/JGWwiki/KAGRA/Subgroups/VIS/OpsManual/LVDT#stocktake|Staocktake]] * Buy 10 sets * Check the broken boards in Mitaka * Enzo will bring the broken LVDT box into the site again to check if the remaining channels are alive or not. |
Line 54: | Line 122: |
* Takahashi: * Okutomi: * Sato: |
* Takahashi: 23 -27 * Okutomi: 23 - * Sato: 24 -27 |
Line 58: | Line 126: |
* Mark: * Hirata: * Enzo: |
* Mark: 23 -27 * Hirata: 23 -25 * Enzo: 23 -27 |
Line 63: | Line 131: |
* Fujii: * Tanioka: |
* Fujii: 23 -27 * Tanioka: 23 - |
Line 66: | Line 134: |
* Kozu (ICRR): | * Kozu (ICRR): 25 -27 |
Line 72: | Line 140: |
* Okutomi: | * Okutomi: - 5/3 |
Line 75: | Line 143: |
* Mark: | * Mark: 4/31 - 5/2 |
Line 77: | Line 145: |
* Enzo: | * Enzo: 4/31 - 5/2 |
Line 81: | Line 149: |
* Tanioka: | * Tanioka: - 5/6 |
Line 83: | Line 151: |
* Kozu (ICRR): | * Kozu (ICRR): 4/30 - 5/1 |
Agenda/Minutes of the VIS Meeting on 2018/4/20
2018/4/20 13:30 - 15:20
Participants: Mark, Shoda, Takahashi, Sato, Aso, Okutomi, Ishizaki, Tanioka, Eleonora, Enzo, Fujii, Hirata, Akutsu, Tanaka
Progress report
Schedule Chart
Type-A : (PDF/MPP)
Type-B: (PDF/MPP)
Type-A (Takahashi)
Past week report
[X-front]
- Bent and formed six blades to mount on the TF base.
- Mounted the blades on the TF base.
- Put the damper ring with magnets on the F1.
- Mounted the PI on the bridge frame with the maraging wire.
- Suspended the filter chain from the TF. Needed load was about 700kg for the TF in spite of target load of 580kg.
- Removed one blade and rearranged two blade. The TF could work without additional load.
- Suspended the damper ring from the TF base. One hook screw galled.
- Cabled between the F1 and the upper small hexagon.
- Inserted the wire clamp.
- Dismounted the PI and bridge frame.
- Checked the cable connections.
- Lifted down the F1 into the corrugate tube. The top ring sit on the frame lock.
- Installed the PI into the top chamber.
Plan for coming weeks
[X-front]
- Cable to the feedthroughs.
- Set the ACCs.
- Calibrate the LVDTs for the BF damper and the IP.
Type B (Mark)
Report for week of 4/9
- We packed away the SRM SF and BF.
- After several failed attempts with one secondary prism, Mark finished the SR3 prism/magnet gluing.
- Tanioka-kun built two IRMs (less OSEMs).
- Enzo built an RM.
- Kozu-kun and Enzo calibrated one set of 6 IM OSEMs for SR3. (6 OSEMs for SRM remain to be done.)
- Hirata-san aligned the assembly frame, installed the interface bars and IM ring, and installed the IM.
- Eleonora and Izumi-san revisited the BS length to tilt coupling, which had degraded, and got it working again.
Plan for week of 4/23
- Shoda-san at Mitaka.
- Hirata-san at Kamioka Mon-Wed, then Mitaka.
- Kozu-kun at Kamioka Wed-Fri (but may be working with PEM on Fri).
- Others (Mark, Enzo, Tanioka-kun) at Kamioka full week
- --
- Continue SR3 Hang
- Hang optic.
- Hang RM.
- Cable RM OSEMs.
Plan for week of 4/30
- Shoda-san at Mitaka.
- Mark, Enzo at Kamioka Mon-Wed or TBD.
- Others having fun doing Golden Week stuff.
- --
- Observe KAGRA Phase 1 operations, assist if problems arise.
- Do BF TFs.
- Continue SR3 hang.
To-Do Lists, Schedule
Vacation Info
- Fabian vacation, 3/26-4/27 (then gone).
Type-Bp (Shoda)
Past week report
Plan for coming weeks
OMMT & OSTM (Ohishi)
Past week report
Plan for coming weeks
LVDT Driver (Tanaka)
Past week report
Plan for coming weeks
Other site works
Safety
- Incidents: no incident
- Foreseen risks
- Type-A:
- Type-B:
- Type-Bp:
Discussion
Composite SRM design (Shoda)
- After some discussions, a new idea of gluing the HR surface to a PEEK ring emerged.
- Shoda-san will elaborate on the idea and report to the relevant people.
ETMY tower repair (Takahashi, Okutomi)
- According to Okutomi-kun's TF measurements, even the F3 stage may be stuck.
- We should be able to release the F3 GAS by adjusting the mass on the BF from the cross-tube.
- We will try this before O3.
- Takahashi-san will make a schedule for the ETMY repair works by the next VIS meeting.
=== Phase 1 Operation Reschedule
- Mark, Enzo, Okutomi, Tanioka, Kozu will join the operation.
- Shoda-san will join remotely through Skype or something (communication method will be announced by Mark)
LVDT drivers
- Buy 10 sets
- Check the broken boards in Mitaka
- Enzo will bring the broken LVDT box into the site again to check if the remaining channels are alive or not.
Travel Plans
- Travel (Week of 4/23):
- Takahashi: 23 -27
- Okutomi: 23 -
- Sato: 24 -27
- Ishizaki:
- Mark: 23 -27
- Hirata: 23 -25
- Enzo: 23 -27
- Shoda:
- Ohishi:
- Fujii: 23 -27
- Tanioka: 23 -
- Tanaka:
- Kozu (ICRR): 25 -27
- Arai (ICRR):
- Travel (Week of 4/30):
- Takahashi:
- Okutomi: - 5/3
- Sato:
- Ishizaki:
- Mark: 4/31 - 5/2
- Hirata:
- Enzo: 4/31 - 5/2
- Shoda:
- Ohishi:
- Fujii:
- Tanioka: - 5/6
- Tanaka:
- Kozu (ICRR): 4/30 - 5/1
- Arai (ICRR):
Next meeting
On 2018/4/27(Fri)