= Agenda/Minutes of the VIS Meeting on 2018/4/20 = 2018/4/20 13:30 - 15:20 Participants: Mark, Shoda, Takahashi, Sato, Aso, Okutomi, Ishizaki, Tanioka, Eleonora, Enzo, Fujii, Hirata, Akutsu, Tanaka == Progress report == === Schedule Chart === Type-A : ([[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7320|PDF/MPP]]) Type-B: ([[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7779|PDF/MPP]]) === Type-A (Takahashi) === ==== Past week report ==== [X-front] * Bent and formed six blades to mount on the TF base. * Mounted the blades on the TF base. * Put the damper ring with magnets on the F1. * Mounted the PI on the bridge frame with the maraging wire. * Suspended the filter chain from the TF. Needed load was about 700kg for the TF in spite of target load of 580kg. * Removed one blade and rearranged two blade. The TF could work without additional load. * Suspended the damper ring from the TF base. One hook screw galled. * Cabled between the F1 and the upper small hexagon. * Inserted the wire clamp. * Dismounted the PI and bridge frame. * Checked the cable connections. * Lifted down the F1 into the corrugate tube. The top ring sit on the frame lock. * Installed the PI into the top chamber. ==== Plan for coming weeks ==== [X-front] * Cable to the feedthroughs. * Set the ACCs. * Calibrate the LVDTs for the BF damper and the IP. === Type B (Mark) === ==== Report for week of 4/9 ==== * We packed away the SRM SF and BF. * After several failed attempts with one secondary prism, Mark finished the SR3 prism/magnet gluing. * Tanioka-kun built two IRMs (less OSEMs). * Enzo built an RM. * Kozu-kun and Enzo calibrated one set of 6 IM OSEMs for SR3. (6 OSEMs for SRM remain to be done.) * Hirata-san aligned the assembly frame, installed the interface bars and IM ring, and installed the IM. * Eleonora and Izumi-san revisited the BS length to tilt coupling, which had degraded, and got it working again. ==== Plan for week of 4/23 ==== * Shoda-san at Mitaka. * Hirata-san at Kamioka Mon-Wed, then Mitaka. * Kozu-kun at Kamioka Wed-Fri (but may be working with PEM on Fri). * Others (Mark, Enzo, Tanioka-kun) at Kamioka full week * -- * Continue SR3 Hang * Hang optic. * Hang RM. * Cable RM OSEMs. ==== Plan for week of 4/30 ==== * Shoda-san at Mitaka. * Mark, Enzo at Kamioka Mon-Wed or TBD. * Others having fun doing Golden Week stuff. * -- * Observe KAGRA Phase 1 operations, assist if problems arise. * Do BF TFs. * Continue SR3 hang. ==== To-Do Lists, Schedule ==== * [[KAGRA/Subgroups/VIS/TypeB/March2018]] * [[KAGRA/Subgroups/VIS/TypeB/April2018]] * [[KAGRA/Subgroups/VIS/TypeB/ToDoBS]] * [[KAGRA/Subgroups/VIS/TypeB/ToDoSR]] * [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7779|JGW-L1807779-v1 Type B Schedule (SR)]] ==== Vacation Info ==== * Fabian vacation, 3/26-4/27 (then gone). === Type-Bp (Shoda) === ==== Past week report ==== ==== Plan for coming weeks ==== === OMMT & OSTM (Ohishi) === ==== Past week report ==== ==== Plan for coming weeks ==== === LVDT Driver (Tanaka) === ==== Past week report ==== ==== Plan for coming weeks ==== === Other site works === === Safety === * Incidents: no incident * Foreseen risks * Type-A: * Type-B: * Type-Bp: == Discussion == === Composite SRM design (Shoda) === * After some discussions, a new idea of gluing the HR surface to a PEEK ring emerged. * Shoda-san will elaborate on the idea and report to the relevant people. === ETMY tower repair (Takahashi, Okutomi) === * According to Okutomi-kun's TF measurements, even the F3 stage may be stuck. * We should be able to release the F3 GAS by adjusting the mass on the BF from the cross-tube. * We will try this before O3. * Takahashi-san will make a schedule for the ETMY repair works by the next VIS meeting. === Phase 1 Operation Reschedule === * [[https://www.dropbox.com/s/u685czkj8gddd52/Chief180402%E3%80%80Phase1%20after%20experiments.pdf?dl=0|New schedule]] * Mark, Enzo, Okutomi, Tanioka, Kozu will join the operation. * Shoda-san will join remotely through Skype or something (communication method will be announced by Mark) === LVDT drivers === * [[http://gwwiki.icrr.u-tokyo.ac.jp/JGWwiki/KAGRA/Subgroups/VIS/OpsManual/LVDT#stocktake|Staocktake]] * Buy 10 sets * Check the broken boards in Mitaka * Enzo will bring the broken LVDT box into the site again to check if the remaining channels are alive or not. === OSEM rebuild === * Two SR OSEMs have low open voltage * We will replace the LED and PDs on them. * Shoda-san will send spare parts from Mitaka to Kamioka. == Travel Plans == * Travel (Week of 4/23): * Takahashi: 23 -27 * Okutomi: 23 - * Sato: 24 -27 * Ishizaki: * Mark: 23 -27 * Hirata: 23 -25 * Enzo: 23 -27 * Shoda: * Ohishi: * Fujii: 23 -27 * Tanioka: 23 - * Tanaka: * Kozu (ICRR): 25 -27 * Arai (ICRR): * Travel (Week of 4/30): * Takahashi: * Okutomi: - 5/3 * Sato: * Ishizaki: * Mark: 4/31 - 5/2 * Hirata: * Enzo: 4/31 - 5/2 * Shoda: * Ohishi: * Fujii: * Tanioka: - 5/6 * Tanaka: * Kozu (ICRR): 4/30 - 5/1 * Arai (ICRR): == Next meeting == On 2018/4/27(Fri)