Size: 1843
Comment:
|
← Revision 14 as of 2018-07-27 13:23:24 ⇥
Size: 5559
Comment:
|
Deletions are marked like this. | Additions are marked like this. |
Line 3: | Line 3: |
2018/7/20 13:30 - | 2018/7/20 13:30 - 15:00 |
Line 7: | Line 7: |
Participants: | Participants: Mark, Takahashi, Aso, Panwei, Terrence, Fabian, Enzo, Hirata, Pan, Okutomi, Sato, Tanioka, Ishizaki, Fujii, Lucia, Eleonora, Tanaka, Shoda, Kozu |
Line 17: | Line 17: |
[SRM] * Dismounted the top filter for SRM from the IP for Type-A. Packed the IP to the box. * Combined the top filter and the IP. [Y-front] * Transported the IPs from/to the first floor. * Measured the transfer functions of the BF/F3/F2 by the digital system. * Cabled in the F1. * Assembled the cup of F1 (Cu plates, connector plates) and closed the cup. * Measured the weight of F1. [X-front] * Evaluated the ACCs. * Fixed the cables between the cryo-payload (CP) and the BF at the lower points on the wire. * Connected the cables to the BF. * The CP was installed and suspended from the BF. * Adjusted the height of CP. The height of BF was set to 67.5mm. |
|
Line 18: | Line 37: |
* Setting of the F1 in Y-front. * Setting of the top filter in X-front. |
|
Line 20: | Line 41: |
==== Past week report ==== ==== Plan for coming weeks ==== |
==== Report for week of 7/17 ==== * We checked the polarity of the IP LVDTs and flipped coil connections to get the standard arrangement. * We debugged an issue where one of the LVDT actuators had half the magnets in backwards resulting in no force. * We calibrated all the PI LVDTs. * We set the SF damper ring gap. * We prepped the suspension for craning, moved it into the tank and hooked the LBB damper ring rods. * Type A merged the SRM F0 with the correct IP, and we moved it out of the way (to the second floor behind the SRM tank). * We installed more cable clamps on the SR2 PI. |
Line 23: | Line 50: |
==== Plan for week of 7/23 ==== * Mark, Enzo, Fabian, Kozu-kun, Terrence, Panwei at Kamioka Mon-Fri. * Hirata-san at Kamioka Mon-Thu. * Mirapro moves assembly frame ≈7/25 (Wed). ===== SR3 ===== * Unlock suspension. * Rearrange cables. * Test. ===== SR2 ===== * Finish PI prep. * Crane into AF, suspend. * Start cable routing. ===== SRM ===== * Prepare to assemble SRM metal mass (most parts due Wed 7/25). * Help Mirapro with AF move. * Start rebuild of top filter of PI #2. ==== To-Do Lists, Schedule ==== * [[KAGRA/Subgroups/VIS/TypeB/ToDoBS]] * [[KAGRA/Subgroups/VIS/TypeB/ToDoSR]] * [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7779|JGW-L1807779 Type B Schedule (SR)]] ==== Vacation Info ==== * Hirata-san at Mitaka 7/27. * Terrence: 8/24-26 f2f, then returns to Hong Kong. * Enzo: 9/14 JPS, 9/15 through 10/8 vacation in Chile. |
|
Line 29: | Line 83: |
* IMMT2 screw replacement finished (July 9th-20th). * Measure TF in the week after next. * Got a quotation of OMMT/OSTM. |
|
Line 30: | Line 87: |
* Order OMMT/OSTM mechanical parts. | |
Line 41: | Line 98: |
* Incidents: | * Incidents: no incident |
Line 44: | Line 101: |
* Type-A: * Type-B: |
* Type-A: Crane work * Type-B: Crane work, holes in the 2F |
Line 49: | Line 106: |
* [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=5539|klog]] * F2 is stuck * We will leave it stuck for O3 * Geophones or Accelerometers ? * We will use Geophones for ITMs too. * We need to buy 6 more geophones. However the lead time can be long |
|
Line 50: | Line 113: |
* To be confirmed in the next week | |
Line 51: | Line 115: |
* Immediately necessary: 2.4m cables for OSEMs (x2), 5 Type-1 cables * Sato-san will order them soon * We need to make more Type-1 cables by the end of September * We need more cable material for this * Takahashi-san is waiting for a quote for PTFE cable material |
|
Line 52: | Line 121: |
* We will request 2 slots | |
Line 53: | Line 123: |
* Survey to point out different aspects that should be covered in a introductory lecture for KAGRA. [[https://docs.google.com/document/d/1jf9jNfU-ZDP0fjNZVo6yp0S7q91V8aa7qck7Mme0hrU/edit?usp=sharing|survey]] | |
Line 56: | Line 127: |
* Takahashi: | * Takahashi: 23 - 27 |
Line 58: | Line 129: |
* Sato: * Lucia: |
* Sato: 23 - 27 * Lucia: 23 - 27 |
Line 61: | Line 132: |
* Mark: * Hirata: * Enzo: * Panwei * Terrence: |
* Mark: 23 - 27 * Hirata: 23 - 26 * Enzo: 23 - 27 * Panwei: 23 - 27 * Terrence: 23 - 27 |
Line 68: | Line 139: |
* Fujii: * Tanioka: |
* Fujii: 24 - 27 * Tanioka: |
Line 71: | Line 142: |
* Kozu (ICRR): | * Kozu (ICRR): 23 - 26 |
Line 73: | Line 144: |
* Eleonora: 23 - 26 * Hashimoto: 23 - 27 |
|
Line 75: | Line 148: |
* Takahashi: | * Takahashi: |
Line 77: | Line 150: |
* Sato: * Lucia: |
* Sato: 7/30 - 8/3 * Lucia: 7/30 - 8/3 |
Line 80: | Line 153: |
* Mark: * Hirata: * Enzo: * Terrence: * Panwei |
* Mark: 7/30 - 8/3 * Hirata: 7/30 - 8/3 * Enzo: 7/30 - 8/3 * Terrence: 7/30 - 8/3 * Panwei 7/30 - 8/3 |
Line 87: | Line 160: |
* Fujii: * Tanioka: |
* Fujii: 7/30 - 8/3 * Tanioka: 7/30 - 8/3 |
Line 90: | Line 163: |
* Kozu (ICRR): | * Kozu (ICRR): 7/30 - 8/3 |
Line 92: | Line 165: |
* Hatoya: 8/2 - 8/3 == Next meeting == On 2018/7/27(Fri) |
Agenda/Minutes of the VIS Meeting on 2018/7/20
2018/7/20 13:30 - 15:00
Participants: Mark, Takahashi, Aso, Panwei, Terrence, Fabian, Enzo, Hirata, Pan, Okutomi, Sato, Tanioka, Ishizaki, Fujii, Lucia, Eleonora, Tanaka, Shoda, Kozu
Progress report
Schedule Chart
Type-A : (PDF/MPP)
Type-B: (PDF/MPP)
Type-A (Takahashi)
Past week report
[SRM]
- Dismounted the top filter for SRM from the IP for Type-A. Packed the IP to the box.
- Combined the top filter and the IP.
[Y-front]
- Transported the IPs from/to the first floor.
- Measured the transfer functions of the BF/F3/F2 by the digital system.
- Cabled in the F1.
- Assembled the cup of F1 (Cu plates, connector plates) and closed the cup.
- Measured the weight of F1.
[X-front]
- Evaluated the ACCs.
- Fixed the cables between the cryo-payload (CP) and the BF at the lower points on the wire.
- Connected the cables to the BF.
- The CP was installed and suspended from the BF.
- Adjusted the height of CP. The height of BF was set to 67.5mm.
Plan for coming weeks
- Setting of the F1 in Y-front.
- Setting of the top filter in X-front.
Type B (Mark)
Report for week of 7/17
- We checked the polarity of the IP LVDTs and flipped coil connections to get the standard arrangement.
- We debugged an issue where one of the LVDT actuators had half the magnets in backwards resulting in no force.
- We calibrated all the PI LVDTs.
- We set the SF damper ring gap.
- We prepped the suspension for craning, moved it into the tank and hooked the LBB damper ring rods.
- Type A merged the SRM F0 with the correct IP, and we moved it out of the way (to the second floor behind the SRM tank).
- We installed more cable clamps on the SR2 PI.
Plan for week of 7/23
- Mark, Enzo, Fabian, Kozu-kun, Terrence, Panwei at Kamioka Mon-Fri.
- Hirata-san at Kamioka Mon-Thu.
- Mirapro moves assembly frame ≈7/25 (Wed).
SR3
- Unlock suspension.
- Rearrange cables.
- Test.
SR2
- Finish PI prep.
- Crane into AF, suspend.
- Start cable routing.
SRM
- Prepare to assemble SRM metal mass (most parts due Wed 7/25).
- Help Mirapro with AF move.
- Start rebuild of top filter of PI #2.
To-Do Lists, Schedule
Vacation Info
- Hirata-san at Mitaka 7/27.
- Terrence: 8/24-26 f2f, then returns to Hong Kong.
- Enzo: 9/14 JPS, 9/15 through 10/8 vacation in Chile.
Type-Bp (Shoda)
Past week report
Plan for coming weeks
OMMT & OSTM (Ohishi)
Past week report
- IMMT2 screw replacement finished (July 9th-20th).
- Measure TF in the week after next.
- Got a quotation of OMMT/OSTM.
Plan for coming weeks
- Order OMMT/OSTM mechanical parts.
VIS electronics (Tanaka)
Past week report
Plan for coming weeks
Other site works
- July 26 11:30 - 12:30: Monthly crane inspection
- Sept 10(Mon): Planned power outage
Safety
- Incidents: no incident
- Foreseen risks
- Type-A: Crane work
- Type-B: Crane work, holes in the 2F
Discussion
- ETMX F2 status
- F2 is stuck
- We will leave it stuck for O3
- Geophones or Accelerometers ?
- We will use Geophones for ITMs too.
- We need to buy 6 more geophones. However the lead time can be long
- SR2 TF optimal load problem
- To be confirmed in the next week
- SR cable procurement
- Immediately necessary: 2.4m cables for OSEMs (x2), 5 Type-1 cables
- Sato-san will order them soon
- We need to make more Type-1 cables by the end of September
- We need more cable material for this
- Takahashi-san is waiting for a quote for PTFE cable material
- Immediately necessary: 2.4m cables for OSEMs (x2), 5 Type-1 cables
- VIS talk at the F2F in Toyama U
- We will request 2 slots
VIS introduction page
Survey to point out different aspects that should be covered in a introductory lecture for KAGRA. survey
Travel Plans
- Travel (Week of 7/23):
- Takahashi: 23 - 27
- Okutomi:
- Sato: 23 - 27
- Lucia: 23 - 27
- Ishizaki:
- Mark: 23 - 27
- Hirata: 23 - 26
- Enzo: 23 - 27
- Panwei: 23 - 27
- Terrence: 23 - 27
- Shoda:
- Ohishi:
- Fujii: 24 - 27
- Tanioka:
- Tanaka:
- Kozu (ICRR): 23 - 26
- Arai (ICRR):
- Eleonora: 23 - 26
- Hashimoto: 23 - 27
- Travel (Week of 7/30):
- Takahashi:
- Okutomi:
- Sato: 7/30 - 8/3
- Lucia: 7/30 - 8/3
- Ishizaki:
- Mark: 7/30 - 8/3
- Hirata: 7/30 - 8/3
- Enzo: 7/30 - 8/3
- Terrence: 7/30 - 8/3
- Panwei 7/30 - 8/3
- Shoda:
- Ohishi:
- Fujii: 7/30 - 8/3
- Tanioka: 7/30 - 8/3
- Tanaka:
- Kozu (ICRR): 7/30 - 8/3
- Arai (ICRR):
- Hatoya: 8/2 - 8/3
Next meeting
On 2018/7/27(Fri)