==== Past week report ====
==== Plan for coming weeks ====
==== Report for week of 7/17 ====
 * We checked the polarity of the IP LVDTs and flipped coil connections to get the standard arrangement.
 * We debugged an issue where one of the LVDT actuators had half the magnets in backwards resulting in no force.
 * We calibrated all the PI LVDTs.
 * We set the SF damper ring gap.
 * We prepped the suspension for craning, moved it into the tank and hooked the LBB damper ring rods.
 * Type A merged the SRM F0 with the correct IP, and we moved it out of the way (to the second floor behind the SRM tank).
 * We installed more cable clamps on the SR2 PI.
Line 44: Line 50:
==== Plan for week of 7/23 ====
 * Mark, Enzo, Fabian, Kozu-kun, Terrence, Panwei at Kamioka Mon-Fri.
 * Hirata-san at Kamioka Mon-Thu.
 * Mirapro moves assembly frame ≈7/25 (Wed).

===== SR3 =====
 * Unlock suspension.
 * Rearrange cables.
 * Test.
===== SR2 =====
 * Finish PI prep.
 * Crane into AF, suspend.
 * Start cable routing.
===== SRM =====
 * Prepare to assemble SRM metal mass (most parts due Wed 7/25).
 * Help Mirapro with AF move.
 * Start rebuild of top filter of PI #2.

==== To-Do Lists, Schedule ====
 * [[KAGRA/Subgroups/VIS/TypeB/ToDoBS]]
 * [[KAGRA/Subgroups/VIS/TypeB/ToDoSR]]
 * [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7779|JGW-L1807779 Type B Schedule (SR)]]

==== Vacation Info ====
 * Hirata-san at Mitaka 7/27.
 * Terrence: 8/24-26 f2f, then returns to Hong Kong.
 * Enzo: 9/14 JPS, 9/15 through 10/8 vacation in Chile.

Agenda/Minutes of the VIS Meeting on 2018/7/20

2018/7/20 13:30 -

Zoom Meeting

Participants:

Progress report

Schedule Chart

Type-A : (PDF/MPP)

Type-B: (PDF/MPP)

Type-A (Takahashi)

Past week report

[SRM]

  • Dismounted the top filter for SRM from the IP for Type-A. Packed the IP to the box.
  • Combined the top filter and the IP.

[Y-front]

  • Transported the IPs from/to the first floor.
  • Measured the transfer functions of the BF/F3/F2 by the digital system.
  • Cabled in the F1.
  • Assembled the cup of F1 (Cu plates, connector plates) and closed the cup.
  • Measured the weight of F1.

[X-front]

  • Evaluated the ACCs.
  • Fixed the cables between the cryo-payload (CP) and the BF at the lower points on the wire.
  • Connected the cables to the BF.
  • The CP was installed and suspended from the BF.
  • Adjusted the height of CP. The height of BF was set to 67.5mm.

Plan for coming weeks

  • Setting of the F1 in Y-front.
  • Setting of the top filter in X-front.

Type B (Mark)

Report for week of 7/17

  • We checked the polarity of the IP LVDTs and flipped coil connections to get the standard arrangement.
  • We debugged an issue where one of the LVDT actuators had half the magnets in backwards resulting in no force.
  • We calibrated all the PI LVDTs.
  • We set the SF damper ring gap.
  • We prepped the suspension for craning, moved it into the tank and hooked the LBB damper ring rods.
  • Type A merged the SRM F0 with the correct IP, and we moved it out of the way (to the second floor behind the SRM tank).
  • We installed more cable clamps on the SR2 PI.

Plan for week of 7/23

  • Mark, Enzo, Fabian, Kozu-kun, Terrence, Panwei at Kamioka Mon-Fri.
  • Hirata-san at Kamioka Mon-Thu.
  • Mirapro moves assembly frame ≈7/25 (Wed).

SR3
  • Unlock suspension.
  • Rearrange cables.
  • Test.

SR2
  • Finish PI prep.
  • Crane into AF, suspend.
  • Start cable routing.

SRM
  • Prepare to assemble SRM metal mass (most parts due Wed 7/25).
  • Help Mirapro with AF move.
  • Start rebuild of top filter of PI #2.

To-Do Lists, Schedule

Vacation Info

  • Hirata-san at Mitaka 7/27.
  • Terrence: 8/24-26 f2f, then returns to Hong Kong.
  • Enzo: 9/14 JPS, 9/15 through 10/8 vacation in Chile.

Type-Bp (Shoda)

Past week report

Plan for coming weeks

OMMT & OSTM (Ohishi)

Past week report

Plan for coming weeks

VIS electronics (Tanaka)

Past week report

Plan for coming weeks

Other site works

  • July 26 11:30 - 12:30: Monthly crane inspection
  • Sept 10(Mon): Planned power outage

Safety

  • Incidents:
  • Foreseen risks
    • Type-A:
    • Type-B:

Discussion

  • ETMX F2 status
  • SR2 TF optimal load problem
  • SR cable procurement
  • VIS talk at the F2F in Toyama U
  • VIS introduction page

  • Survey to point out different aspects that should be covered in a introductory lecture for KAGRA.

Travel Plans

  • Travel (Week of 7/23):
    • Takahashi:
    • Okutomi:
    • Sato:
    • Lucia:
    • Ishizaki:
    • Mark:
    • Hirata:
    • Enzo:
    • Panwei
    • Terrence:
    • Shoda:
    • Ohishi:
    • Fujii:
    • Tanioka:
    • Tanaka:
    • Kozu (ICRR):
    • Arai (ICRR):
  • Travel (Week of 7/30):
    • Takahashi:
    • Okutomi:
    • Sato:
    • Lucia:
    • Ishizaki:
    • Mark:
    • Hirata:
    • Enzo:
    • Terrence:
    • Panwei
    • Shoda:
    • Ohishi:
    • Fujii:
    • Tanioka:
    • Tanaka:
    • Kozu (ICRR):
    • Arai (ICRR):

Next meeting

On 2018/7/27(Fri)