Differences between revisions 8 and 9
Revision 8 as of 2018-07-20 14:58:07
Size: 4593
Editor: YoichiAso
Comment:
Revision 9 as of 2018-07-20 14:58:16
Size: 4598
Editor: YoichiAso
Comment:
Deletions are marked like this. Additions are marked like this.
Line 3: Line 3:
2018/7/20 13:30 - 2018/7/20 13:30 - 15:00

Agenda/Minutes of the VIS Meeting on 2018/7/20

2018/7/20 13:30 - 15:00

Zoom Meeting

Participants:

Progress report

Schedule Chart

Type-A : (PDF/MPP)

Type-B: (PDF/MPP)

Type-A (Takahashi)

Past week report

[SRM]

  • Dismounted the top filter for SRM from the IP for Type-A. Packed the IP to the box.
  • Combined the top filter and the IP.

[Y-front]

  • Transported the IPs from/to the first floor.
  • Measured the transfer functions of the BF/F3/F2 by the digital system.
  • Cabled in the F1.
  • Assembled the cup of F1 (Cu plates, connector plates) and closed the cup.
  • Measured the weight of F1.

[X-front]

  • Evaluated the ACCs.
  • Fixed the cables between the cryo-payload (CP) and the BF at the lower points on the wire.
  • Connected the cables to the BF.
  • The CP was installed and suspended from the BF.
  • Adjusted the height of CP. The height of BF was set to 67.5mm.

Plan for coming weeks

  • Setting of the F1 in Y-front.
  • Setting of the top filter in X-front.

Type B (Mark)

Report for week of 7/17

  • We checked the polarity of the IP LVDTs and flipped coil connections to get the standard arrangement.
  • We debugged an issue where one of the LVDT actuators had half the magnets in backwards resulting in no force.
  • We calibrated all the PI LVDTs.
  • We set the SF damper ring gap.
  • We prepped the suspension for craning, moved it into the tank and hooked the LBB damper ring rods.
  • Type A merged the SRM F0 with the correct IP, and we moved it out of the way (to the second floor behind the SRM tank).
  • We installed more cable clamps on the SR2 PI.

Plan for week of 7/23

  • Mark, Enzo, Fabian, Kozu-kun, Terrence, Panwei at Kamioka Mon-Fri.
  • Hirata-san at Kamioka Mon-Thu.
  • Mirapro moves assembly frame ≈7/25 (Wed).

SR3
  • Unlock suspension.
  • Rearrange cables.
  • Test.

SR2
  • Finish PI prep.
  • Crane into AF, suspend.
  • Start cable routing.

SRM
  • Prepare to assemble SRM metal mass (most parts due Wed 7/25).
  • Help Mirapro with AF move.
  • Start rebuild of top filter of PI #2.

To-Do Lists, Schedule

Vacation Info

  • Hirata-san at Mitaka 7/27.
  • Terrence: 8/24-26 f2f, then returns to Hong Kong.
  • Enzo: 9/14 JPS, 9/15 through 10/8 vacation in Chile.

Type-Bp (Shoda)

Past week report

Plan for coming weeks

OMMT & OSTM (Ohishi)

Past week report

Plan for coming weeks

VIS electronics (Tanaka)

Past week report

Plan for coming weeks

Other site works

  • July 26 11:30 - 12:30: Monthly crane inspection
  • Sept 10(Mon): Planned power outage

Safety

  • Incidents:
  • Foreseen risks
    • Type-A:
    • Type-B:

Discussion

  • ETMX F2 status
  • SR2 TF optimal load problem
  • SR cable procurement
  • VIS talk at the F2F in Toyama U
  • VIS introduction page

  • Survey to point out different aspects that should be covered in a introductory lecture for KAGRA. survey

Travel Plans

  • Travel (Week of 7/23):
    • Takahashi: 23 - 27
    • Okutomi:
    • Sato: 23 - 27
    • Lucia: 23 - 27
    • Ishizaki:
    • Mark: 23 - 27
    • Hirata: 23 - 26
    • Enzo: 23 - 27
    • Panwei: 23 - 27
    • Terrence: 23 - 27
    • Shoda:
    • Ohishi:
    • Fujii: 24 - 27
    • Tanioka:
    • Tanaka:
    • Kozu (ICRR): 23 - 26
    • Arai (ICRR):
    • Eleonora: 23 - 26
    • Hashimoto: 23 - 27
  • Travel (Week of 7/30):
    • Takahashi:
    • Okutomi:
    • Sato: 7/30 - 8/3
    • Lucia: 7/30 - 8/3
    • Ishizaki:
    • Mark: 7/30 - 8/3
    • Hirata: 7/30 - 8/3
    • Enzo: 7/30 - 8/3
    • Terrence: 7/30 - 8/3
    • Panwei 7/30 - 8/3
    • Shoda:
    • Ohishi:
    • Fujii: 7/30 - 8/3
    • Tanioka: 7/30 - 8/3
    • Tanaka:
    • Kozu (ICRR): 7/30 - 8/3
    • Arai (ICRR):
    • Hatoya: 8/2 - 8/3

Next meeting

On 2018/7/27(Fri)

KAGRA/Subgroups/VIS/VISMinutes20180720 (last edited 2018-07-27 13:23:24 by NaokoOhishi)