= Agenda/Minutes of the VIS Meeting on 2018/10/19 = 2018/10/19 13:30 - 14:50 [[https://zoom.us/j/203743987|Zoom Meeting]] Participants:Mark, Okutomi, Takahashi, Aso, Ohishi, Enzo, Sato, Hirata, Fabian, Fujii, Lucia == Progress report == === Schedule Chart === Type-A : ([[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7320|PDF/MPP]]) Type-B: ([[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7779|PDF/MPP]]) Type-C: ([[ https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=9013|XLSX]]) === Type-A (Takahashi) === ==== Past week report ==== [X-front] * Corrected the tilt of IP base by jack up/down of the corn bellows. * Adjusted the position of IP by the stepping motors. * Aligned the TM by the yaw picomoter in the BF. [X-end] * Corrected the tilt of IP base by jack up/down of the corn bellows. * It was difficult to adjust the position of IP by the stepping motors due to the tight stopper setting. * Vented the EXV chamber and open the top chamber. * Released the stopper for IP more. * Adjusted the position of IP by hand/stepping motors. * Aligned the TM by the yaw picomoter in the BF. * Closed the top chamber and started the evacuation. * Followed the drift of IP position by the stepping motors during the evacuation. [Y-front] * Investigated the 70Hz peak in the spectrum of IP LVDTs. Changed the modulation frequency from 10,000Hz to 10,003Hz. * Designing the yaw stepping motor mechanism. We need to procure 4 more motors. ==== Plan for coming weeks ==== [Y-front] * Replacement of the FR parts for BF. (10/22, 23) [Y-end] * Assembly of the geophone pods and installation. (10/24) === Type B (Mark) === ==== Report for week of 10/15 ==== ===== SRM ===== * We received the fourth feedthrough we had been waiting for and installed it on the AF. * Fabian added the cables between the FE computer and the ADC/DAC boxes, and we checked that we were getting IO in the real-time model. * Fabian and Enzo connected up the Sat Amps. * Fabian double-checked the optic pitch, got the IRM nicely aligned to the IM, cabled IM OSEMs V1, V2, V3 and H1, and adjusted those OSEMs in/out to midrange. * Hirata-san set the compression on the F0 to 30 mm and measured the height and frequency as a function of load. He then fixed a loose screw on one of the blade tips and repeated the measurement. The frequency was fairly constant at around 0.5, which will do. He did a mass budget and chose a F1 CuBe spring. We may do a tiny bit more compression if the frequency degrades, and/or choose an even stronger spring if the load capacity is not enough. * Hirata-san took apart and reassembled one of the LBB blade units, which had a badly seated blade. * Hirata-san put cable clamps on the SF and on the PI. We are very short on the PEEK clamp pieces, so he scavenged some from SR2. * We added a new LAN hub for SRM, and configured two stepper drivers as SRM_IP and SRM_GAS. * Late in the week we received extra Type 3-4 cables (thanks to Sato-san for expediting) and were able to cable IM OSEMs H2 and H3, and the BF LVDT. * Enzo made a new batch of feedthrough adapters. ===== SR2 ===== * We finalized the geophone cabling and reinstalled the geophones. * We received the new arc weights, and used some of them to install a basic allotment of 6 38-mm weights on SR3 per the CAD. We then added two extra 19-mm arc weights for tuning and got a good IP frequency of 0.133 Hz. * Apart from the F0 yaw stepper issue and the OL, the SR2 is now more-or-less complete and adjusted mechanically, and just needs software work (control loops etc). We will however have to borrow one of the geophones at some point to do a huddle test with the final batch of new geophones (including those for SRM). Terrence can set up the OL in the week of 10/29. ==== Plan for week of 10/22 ==== * Friday is NAOJ Open Day Prep - no Kamioka work. * Mark, Hirata-san and Fabian at Kamioka Mon-Thu. * Enzo at Kamioka Tue-Thu. ===== SR2 ===== * Monitor disassembly of SR2 AF. * Do a measurement of how much torque is required on the F0 keystone to move the system in yaw. (This will help Sato-san choose a suitable stepper driver for the new design.) * Continue shakedown. * Gather parts for the OL (with help from Simon). ===== SRM ===== * Get optical table from SR2 AF moved to near SR3 and move cables in preparation for geophone test. * Scavenge HPCDs from SR2 and SR3 (currently we only have one for SRM) and organize to get LPCDs modified. * Suspend/weigh/balance the BF/... section. * Build up the AF and SS to the SF level. * Install the SF. ==== Plan for week of 10/29 ==== * Mark, Enzo, Hirata-san, Fabian and Terrence at Kamioka Mon-Fri. ===== SR2 ===== * Set up OL. ===== SRM ===== * Continue assembly. ==== To-Do Lists, Schedule ==== * [[KAGRA/Subgroups/VIS/TypeB/ToDoBS]] * [[KAGRA/Subgroups/VIS/TypeB/ToDoSR]] * [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7779|JGW-L1807779 Type B Schedule (SR)]] ==== Vacation/Visitor Info ==== * Terrence: 10/29-11/2 at Kamioka. === Type-Bp (Shoda) === ==== Past week report ==== * Vertical DC control for all the GAS filters have been implemented * PRM LVDTs have much larger coupling from the actuation signal at high frequencies compared with the situation before the black out ==== Plan for coming weeks ==== === OMMT & OSTM (Ohishi) === ==== Past week report ==== *Delivered mechanical parts were almost assembled. *Did cabling from rack to satellite box, and inside chamber. *Mirapro adjusted breadboard level in the vacuum chamber. *OMC was installed by TITech people. ==== Plan for coming weeks ==== *glue magnets and standoff of OMMT1. *cabling (Make flipper, and pico-motor cables) *hang OMMT1 mirror from IM. *Kaihatsu? or Kaihotsu san will come from Toyama University from Tue to Fri. === VIS electronics (Tanaka) === ==== Past week report ==== ==== Plan for coming weeks ==== === Other site works === === Safety === * Incidents: no issue * Foreseen risks * Type-A: No crane work * Type-B: Crane work == Discussion == === Type-A === * Postpone the installation of geophones to ETMY until later half of November === Type-B === * We need 4 more long cables * The delivery of new cable material will be too late (late November) * We will connect shorter cables with soldering * Insulation with PEEK heat shrink tubes or Kapton sheets * Use vacseal to reinforce the connection == Travel Plans == * Travel (Week of 10/22): * Takahashi: 22-24 * Okutomi: * Sato: 22-24 * Lucia: 22-26 * Fabian:22-26 * Mark: 22-25 * Hirata: 22-25 * Enzo:23-25 * Shoda: * Ohishi: * Fujii: * Tanioka: * Tanaka: * Kozu (ICRR): * Arai (ICRR): * Travel (Week of 10/29): * Takahashi: 30 - 2 * Okutomi: * Sato: * Lucia: 29 - 2 * Fabian: 29 - 2 * Mark: 29 - 2 * Hirata: 29 - 2 * Enzo: 29 - 2 * Shoda: * Ohishi: * Fujii: 29 - 2 * Tanioka: * Tanaka: * Terrence: 29 - 2 * Kozu (ICRR): * Arai (ICRR): == Next meeting == On 2018/11/2(Fri)