VIS Weekly Report 2018/11/23
Progress report
Schedule Chart
Type-A : (PDF/MPP)
Type-B: (PDF/MPP)
Type-C: (XLSX)
Type-A (Takahashi)
Past week report
[Y-end]
- Installed the geophone pods. Connected the cables and checked the signals by the digital system.
- Tuned the load for BF adjusting the weight of cryo-payload.
- The height of mirror was set to -6mm from the beam axis.
[Y-front]
- Tuned the load for BF adjusting the weight of cryo-payload.
- The LVDT output for the keystone height in BF was changed from the last time. The sign was flipped.
- Calibrated the LVDT in BF.
- The height of mirror was set -7mm from the beam axis. The height of BF was 64mm.
- Adjusted the keystone height in TF. It was set to -7mm.
Plan for coming weeks
- The week of 12/10: Replace the yaw FR on the TF for Y-front/end.
- The week of 12/17: Replace the yaw FR on the TF for X-front/end.
Type B (Mark)
Past week report
Plan for coming weeks
Type-Bp (Shoda)
Past week report
Plan for coming weeks
OMMT & OSTM (Ohishi)
Past week report
Plan for coming weeks
VIS electronics (Tanaka)
Past week report
Plan for coming weeks
Other site works
- Nov. 28(Wed) 11:30 - : Crane inspection
Safety
- Incidents:
- Foreseen risks
- Type-A:
- Type-B:
Travel Plans
- Travel (Week of 11/26):
- Takahashi: 27-30
- Okutomi:
- Sato:
- Lucia:
- Fabian:
- Mark:
- Hirata:
- Enzo:
- Shoda:
- Ohishi:
- Fujii:
- Tanioka:
- Tanaka:
- Kozu (ICRR):
- Arai (ICRR):
- Travel (Week of 12/3):
- Takahashi:
- Okutomi:
- Sato:
- Lucia:
- Fabian:
- Mark:
- Hirata:
- Enzo:
- Shoda:
- Ohishi:
- Fujii:
- Tanioka:
- Tanaka:
- Kozu (ICRR):
- Arai (ICRR):
Next meeting
On 2018/11/30(Fri)