= VIS Weekly Report 2018/11/23 = == Progress report == === Schedule Chart === Type-A : ([[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7320|PDF/MPP]]) Type-B: ([[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7779|PDF/MPP]]) Type-C: ([[ https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=9013|XLSX]]) === Type-A (Takahashi) === ==== Past week report ==== [Y-end] * Installed the geophone pods. Connected the cables and checked the signals by the digital system. * Tuned the load for BF adjusting the weight of cryo-payload. * The height of mirror was set to -6mm from the beam axis. [Y-front] * Tuned the load for BF adjusting the weight of cryo-payload. * The LVDT output for the keystone height in BF was changed from the last time. The sign was flipped. * Calibrated the LVDT in BF. * The height of mirror was set -7mm from the beam axis. The height of BF was 64mm. * Adjusted the keystone height in TF. It was set to -7mm. ==== Plan for coming weeks ==== * The week of 12/10: Replacement of the yaw FR on the TF for Y-front/end. * The week of 12/17: Replacement of the yaw FR on the TF for X-front/end. === Type B (Mark) === ==== Report for week of 11/12 ==== * BS * Kozu-kun noticed the BS OL was out of range, and Fabian and Fujii-kun investigated. It turns out that the temperature has risen by over 2°C, so all the GAS filters have sagged and several stages are touching. Miyoki-san and Furuta-san are looking at what can be done. * We ordered three more geophone cables in the standard (non-flipped pinout) to save time during the December vent, where we will replace at least two of the preamps to fix issues and take the opportunity to put in non-flipped ones. * SRM * We cabled all the SF/... through to the rack and checked that all items worked. * We did the vertical height survey and found that as with SR2 and SR3, the chain is longer than the CAD, this time by ≈7 mm, and again mostly between the SF and BF. We decided on a keystone height of 11.5 mm (5 mm higher than CAD), which can be achieved with 1 kg more on the SF and 1 kg in reserve for a yaw stepper mechanism. We reset the height of the yoke to give near-zero LVDT output for the new nominal height, and corrected the sensing and actuation signs, but still need to do the calibration. * The final SRM small glass mirror became available, so we had Hirose-san ship it to us so we can install it while the suspension is still on the assembly frame. Hirata-san ordered shims to make up the new recommended thickness of 1.4 mm and a micrometer to check the combination, which should arrive on Monday 11/26. * Enzo took calibration data for the last batch of geophones, for SRM. We had to borrow cables from SR2 because one cable was missing and another was miswired. And it turned out that one of the SR2 cables was defective as well. But if we can find two possibly borrowed by Okutomi-san and rewire one, we should have enough for SR2 and SRM. The geophones appear to be healthy and we will seal them next week. * We raised the PI clear of the assembly frame and unlocked and centered the IP. We calibrated the IP LVDTs, and reversed connections to get positive LVDT output for positive yaw. We borrowed a HPCD from SR3-IM-V for the SRM IP but haven't checked the actuation yet. * SR2 * While we were grabbing geophone cables from SR2, we added extra arc weights to get the IP frequency below 0.1 Hz. * Akutsu-san showed us how to install the OL transmitter support pillar, receiver shelf and viewports. We believe we have the parts to finish setting up the SR2 OL. ==== To-Do Lists, Schedule ==== * [[KAGRA/Subgroups/VIS/TypeB/ToDoBS]] * [[KAGRA/Subgroups/VIS/TypeB/ToDoSR]] * [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7779|JGW-L1807779 Type B Schedule (SR)]] ==== Plan for week of 11/26 ==== * SRM * Clean tools and metal parts for final SRM glass mass. * Swap in final glass mass. * Adjust SF trim mass. * Check/adjust alignment of SS. * Calibrate IP LVDTs. * Add arc weights and geophones. * Improve centering/tuning of IP and SS alignment. * Disconnect cables at feedthroughs, lock suspension. * Crane into tank. * SR2 * Finish OL setup * TFs. * Control loops. ==== Plan for week of 12/3 ==== * f2f Meeting at NAOJ - no Kamioka work. ==== Plan for week of 12/10 ==== * Prepare for vent of BS. * BS work - see [[KAGRA/Subgroups/VIS/TypeB/ToDoBS]]. ==== Vacation/Event Info ==== * Hirata-san at Mitaka, Fri 11/30 (medical check for solvent use). * Enzo at Mitaka, Fri 11/30 (Mitaka day). === Type-Bp (Shoda) === ==== Past week report ==== ==== Plan for coming weeks ==== === OMMT & OSTM (Ohishi) === ==== Past week report ==== ==== Plan for coming weeks ==== === VIS electronics (Tanaka) === ==== Past week report ==== ==== Plan for coming weeks ==== === Other site works === * Nov. 28(Wed) 11:30 - : Crane inspection === Safety === * Incidents: * Foreseen risks * Type-A: * Type-B: == Travel Plans == * Travel (Week of 11/26): * Takahashi: 27-30 * Okutomi: * Sato: * Lucia: * Fabian: 26-30 * Mark: 26-30 * Hirata: 26-29 * Enzo: 26-29 * Shoda: * Ohishi: * Fujii: * Tanioka: * Tanaka: * Kozu (ICRR): * Arai (ICRR): * Travel (Week of 12/3): * Takahashi: * Okutomi: * Sato: * Lucia: * Fabian: * Mark: f2f * Hirata: f2f * Enzo: f2f * Shoda: * Ohishi: * Fujii: * Tanioka: * Tanaka: * Kozu (ICRR): * Arai (ICRR): == Next meeting == On 2018/11/30(Fri)