[Y-end] * Adjusted the TF. Four blades were decompressed by 0.5mm. The height of keystone was set to -12mm. * The coil driver for the TF is not working. * A SUS spanner dropped into the corrugate tube, It might be around the F2 or F3. |
|
Line 20: | Line 25: |
* Tuning of the IP in Y-front in Dec. 26-27. * Replacement of the yaw FR in X-front in Jan. 10-11. |
Agenda/Minutes of the VIS Meeting on 2018/12/21
2018/12/21 13:30 -
Participants:
Progress report
Schedule Chart
Type-A : (PDF/MPP)
Type-B: (PDF/MPP)
Type-C: (XLSX)
Type-A (Takahashi)
Past week report
[Y-end]
- Adjusted the TF. Four blades were decompressed by 0.5mm. The height of keystone was set to -12mm.
- The coil driver for the TF is not working.
- A SUS spanner dropped into the corrugate tube, It might be around the F2 or F3.
Plan for coming weeks
- Tuning of the IP in Y-front in Dec. 26-27.
- Replacement of the yaw FR in X-front in Jan. 10-11.
Type B (Mark)
Past week report
Plan for coming weeks
Type-Bp (Shoda)
Past week report
Plan for coming weeks
OMMT & OSTM (Ohishi)
Past week report
Plan for coming weeks
VIS electronics (Tanaka)
Past week report
Plan for coming weeks
Other site works
Safety
- Incidents:
- Foreseen risks
- Type-A:
- Type-B:
Discussion
Confirmation of the VIS schedule for Jan.
Thesis defence practice
- Kozu-kun and Arai-kun: after the next VIS meeting (12/21)
Travel Plans
- Travel (Week of 12/24):
- Takahashi:
- Okutomi:
- Sato:
- Lucia:
- Fabian:
- Mark:
- Hirata:
- Enzo:
- Shoda:
- Ohishi:
- Fujii:
- Tanioka:
- Tanaka:
- Kozu (ICRR):
- Arai (ICRR):
- Travel (Week of 1/7):
- Takahashi:
- Okutomi:
- Sato:
- Lucia:
- Fabian:
- Mark:
- Hirata:
- Enzo:
- Shoda:
- Ohishi:
- Fujii:
- Tanioka:
- Tanaka:
- Kozu (ICRR):
- Arai (ICRR):
Next meeting
On 2019/1/11(Fri)