Agenda/Minutes of the VIS Meeting on 2019/2/1
2019/2/1 13:30 -
Participants:
Progress report
Schedule Chart
Site work schedule: [[|XLSX]]
Type-A : (PDF/MPP)
Type-B: (PDF/MPP)
Type-C: (XLSX)
Type-A (Takahashi)
Past week report
Plan for coming weeks
- Adjustment of IP in Y-end (Feb 4).
- Finalization of yaw FR in X-front (Feb 5).
- Connection of cryo-payload (Feb. 7)
Type B (Mark)
Past week report
Plan for coming weeks
Type-Bp (Shoda)
Past week report
Plan for coming weeks
OMMT & OSTM (Ohishi)
Past week report
Plan for coming weeks
VIS electronics (Tanaka)
Past week report
Plan for coming weeks
Other site works
Safety
- Incidents:
- Foreseen risks
- Type-A:
- Type-B:
Discussion
Travel Plans
- Travel (Week of 2/4):
- Takahashi: 4-7
- Okutomi:
- Sato: 4-5
- Lucia:
- Fabian:
- Mark:
- Hirata:
- Enzo:
- Shoda:
- Ohishi:
- Fujii:
- Tanioka:
- Tanaka:
- Terrence
- Travel (Week of 2/11):
- Takahashi:
- Okutomi:
- Sato:
- Lucia:
- Fabian:
- Mark:
- Hirata:
- Enzo:
- Shoda:
- Ohishi:
- Fujii:
- Tanioka:
- Terrence
Next meeting
On 2019/2/8(Fri)