= Agenda/Minutes of the VIS Meeting on 2019/5/24 = 2019/5/24 13:30 - 15:00 [[https://zoom.us/j/203743987|Zoom Meeting]] Participants: Hirata, Fabian, Sato, Ishizaki, Shoda, Fujii, Terrence, Aso, Okutomi,Akutsu == Progress report == === Schedule === Site work schedule: [[|XLSX]] === Type-A (Takahashi) === ==== Past week report ==== ==== Plan for coming weeks ==== * I suggest the test of IP control with/without inertial damping in the engineering run in June. === Type B (Mark) === ==== Past week report (written by Fabian) ==== * Terrence implemented a filter for the inertial damping. See entry [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=8905|8905]]. * The highlight of the week is Terrence's measurement of the residual motion of the SR2 optic: as measured by the oplev, it does fulfill the RMS displacement and velocity requirements for lock acquisition and, partially, for the observation mode also. See the report at klog entry [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=8949|8949]]. * The integrated RMS was calculated from 5 Hz to DC because there are some peaks between 8 Hz and 10 Hz and whose origin still has to be clarified. See the report at entries [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=8918|8918]] and [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=8933|8933]]. * After Akutsu-san's suggestion Terrence improved the air shield in two rounds, including a cylindrical cover around the viewport. This reduced the noise by about a factor of 10. * He realized setting up the shield may have slightly changed something in the oplev and carried out another round of diagonalization. * He realized the H3 coil was not working. We fixed it.A cable was disconnected. * The optic residual motion in L showed a large peaks close to 0.2 Hz, which is where the micro-seismic may become apparent. The peak was not seen in P or Y. The inertial damping system is likely not working in a suitable way. The blending frequency is 0.190 Hz which may not be low enough. * At the end measurement of the residual motion reported was carried out with inertial damping only in yaw. * Fabian, Terrence and Fujii-kun measured the settings of the SR2, BS LVDT drivers and one of SR2's. See klogs [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=8941|8941]] , [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=8951|8951]] and [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=8952|8952]]. * Fabian worked more on the calculation of the amount of sensor noise injected: * I imported Panwei's OSEM noise measurements and calculated the virtual sensor noise. * I imported Fujii-kun's measuement of the geophone noise and calculated the virtual sensor noise. * I imported the blending filter * I wrote lots of comments in Sekiguchi-kun's Matlab scripts. * I will write a klog soon with preliminar results. * Fabian submitted and abstract for the Autumn JPS meeting on September. ==== Plan for coming weeks ==== * Terrence will work in the optimization of the inertial damping. * We have to measure the settings of the SR3 LVDT driver. * Fabian will continue with the calculation and prepare a presentation for the conference in Brazil. === Type-Bp (Shoda) === ==== Past week report ==== * Satellite boxes are updated ([[http://klog.icrr.u-tokyo.ac.jp/osl/?r=8928|klog8928]], [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=8912|klog8912]]) * LVDT driver boards are changed ([[http://klog.icrr.u-tokyo.ac.jp/osl/?r=8956|klog8956]]) * Stepping motor BO are connected ([[http://klog.icrr.u-tokyo.ac.jp/osl/?r=8959|klog8959]]) * Moderate WD is installed in PRM, and ready to be installed to the other PRs. ([[http://klog.icrr.u-tokyo.ac.jp/osl/?r=8939|klog8939]]) ==== Plan for coming weeks ==== === OMMT & OSTM (Takahashi) === ==== Past week report ==== * Sato-san is checking the 3D model of TAMA-PO type suspension in the overall model around the OMC. ==== Plan for coming weeks ==== === VIS electronics (Tanaka) === ==== Past week report ==== ==== Plan for coming weeks ==== === Other site works === === Safety === * Incidents: * Foreseen risks * Type-A: * Type-B: == Discussion == * Middle Sized Baffles * [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=10200|JGW-T1910200]] * TO DO List for O3 * Hierarchical control of Type-A (with CRY) * Improved watchdog * Digital * Hardware * Type-B IP damping * Inertial or CMRR ? * Guardian * Type-A guardian missing * Type-Bp guardian improvement * Include the OpLev TM loop * VIS status monitor screens * Operation manuals * L2P diagonalization for all the suspensions * Automatic off-load system == Travel Plans == * Travel (Week of 5/27): * Takahashi: * Sato: * Mark: Holidays * Hirata: * Shoda: * Fujii: 27-28 * Tanioka: * Tanaka: * Terrence: * Travel (Week of 6/3): * Takahashi: * Sato: * Mark: Holidays * Hirata: * Shoda: * Fujii: 4-7 * Tanioka: * Tanaka: * Terrence: * Fabian & Okutomi: Conference in Brazil until June 18th == Next meeting == On 2019/5/31(Fri)