Agenda/Minutes of the VIS Meeting on 2019/6/21
2019/6/21 13:30 -
Participants:
Progress report
Type-A (Takahashi)
Past week report
Plan for coming weeks
Type B (Mark)
Past week report
Plan for coming weeks
Type-Bp (Shoda)
Past week report
Plan for coming weeks
OMMT & OSTM
Past week report
Plan for coming weeks
VIS electronics (Tanaka)
Past week report
Plan for coming weeks
Other site works
Safety
- Incidents:
- Foreseen risks
- Type-A:
- Type-B:
Discussion
Realtime model update policy
- Make local copies of the relevant files (.mdl, MEDM files etc) to modify an existing RTM.
- Once the modifications are complete, you can deploy the modified files by replacing the existing ones.
- Notify the relevant people (kagra-seis and gokagra ML) in advance (more than a day) of the deployment of the modified RTM.
- Deployment should be complete.
- Do not attempt a partial update, such as changing only ETMX. Update all the suspensions of the same kind (Type-A, B, Bp) at once, unless there is a good reason to do so.
- Update MEDM screens at the same time to reflect changes in the RTM.
- People can test the modified RTM during non-interferometer-commissioning time, i.e. in the morning.
- After the test, the RTM should be reverted to the original one, before the interferometer commissioning starts.
Where to put the hardware WDS ?
- Type-Bp: GAS LVDT ?
- Type-B: IP ?
- Type-A: IP ?
Travel Plans
- Travel (Week of 6/24):
- Takahashi:
- Sato:
- Mark:
- Hirata:
- Shoda:
- Fujii:
- Tanioka:
- Tanaka:
- Terrence:
- Travel (Week of 7/1):
- Takahashi:
- Sato:
- Mark:
- Hirata:
- Shoda:
- Fujii:
- Tanioka:
- Tanaka:
- Terrence:
Next meeting
On 2019/6/28(Fri)