Line 16: | Line 16: |
* CRY team will recover the problem of the EYC payload in 28-30th. | |
Line 25: | Line 26: |
=== OMMT & OSTM === | === OMMT & OSTM (Takahashi) === |
Line 27: | Line 28: |
* Modification parts are under manufacturing. * Making the overall 3D model around OMC. |
|
Line 28: | Line 32: |
* Considering the delivery time of OSTM itself, the installation work at the site will be available in September. * Schedule was updated ([[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=10364|PDF/MPP]]). |
|
Line 47: | Line 54: |
* Takahashi: | * Takahashi: 1-2 |
Line 49: | Line 56: |
* Mark: | |
Line 53: | Line 59: |
* Tanioka: | |
Line 60: | Line 65: |
* Mark: | |
Line 64: | Line 68: |
* Tanioka: | |
Line 68: | Line 71: |
Agenda/Minutes of the VIS Meeting on 2019/6/28
2019/6/21 13:00 -
Participants:
BS baffle review
Progress report
Type-A (Takahashi)
Past week report
Plan for coming weeks
- CRY team will recover the problem of the EYC payload in 28-30th.
Type B (Mark)
Past week report
Plan for coming weeks
Type-Bp (Shoda)
Past week report
Plan for coming weeks
OMMT & OSTM (Takahashi)
Past week report
- Modification parts are under manufacturing.
- Making the overall 3D model around OMC.
Plan for coming weeks
- Considering the delivery time of OSTM itself, the installation work at the site will be available in September.
Schedule was updated (PDF/MPP).
VIS electronics (Tanaka)
Past week report
Plan for coming weeks
Other site works
Safety
- Incidents:
- Foreseen risks
- Type-A:
- Type-B:
Discussion
- PRM removal
Travel Plans
- Travel (Week of 7/1):
- Takahashi: 1-2
- Sato:
- Hirata:
- Shoda:
- Fujii:
- Tanaka:
- Terrence:
- Travel (Week of 7/8):
- Takahashi:
- Sato:
- Hirata:
- Shoda:
- Fujii:
- Tanaka:
- Terrence:
Next meeting
On 2019/7/5(Fri)