Line 15: Line 15:
[Okutomi]
 * Monitored the drift of the IP and GAS displacements of the ETMY during the air injection.
 * Tried to offload the DC output to the F3 GAS actuator with the FR, but it resulted that the stepper motor seems stuck.
 * The ETMY chamber is in air pressure.
Line 16: Line 21:
 * CRY team will recover the problem of the EYC payload in 29-30th.  * CRY team will recover the problem of the ETMY payload in 28-30th.
Line 32: Line 37:
 * Considering the delivery time of OSTM itself, the installation work at the site will be available in late August.
 * Schedule([[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=10364|PDF/MPP]])
 * Considering the delivery time of OSTM itself, the installation work at the site will be available in September.
 * Schedule was updated ([[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=10364|PDF/MPP]]).

Agenda/Minutes of the VIS Meeting on 2019/6/28

2019/6/21 13:00 -

Zoom Meeting

Participants:

BS baffle review

Progress report

Type-A (Takahashi)

Past week report

[Okutomi]

  • Monitored the drift of the IP and GAS displacements of the ETMY during the air injection.
  • Tried to offload the DC output to the F3 GAS actuator with the FR, but it resulted that the stepper motor seems stuck.
  • The ETMY chamber is in air pressure.

Plan for coming weeks

  • CRY team will recover the problem of the ETMY payload in 28-30th.

Type B (Mark)

Past week report

Plan for coming weeks

Type-Bp (Shoda)

Past week report

Plan for coming weeks

OMMT & OSTM (Takahashi)

Past week report

  • Modification parts are under manufacturing.
  • Making the overall 3D model around OMC.

Plan for coming weeks

  • Considering the delivery time of OSTM itself, the installation work at the site will be available in September.
  • Schedule was updated (PDF/MPP).

VIS electronics (Tanaka)

Past week report

Plan for coming weeks

Other site works

Safety

  • Incidents:
  • Foreseen risks
    • Type-A:
    • Type-B:

Discussion

  • PRM removal

Travel Plans

  • Travel (Week of 7/1):
    • Takahashi: 1-2
    • Sato:
    • Hirata:
    • Shoda:
    • Fujii:
    • Tanaka:
    • Terrence:
  • Travel (Week of 7/8):
    • Takahashi:
    • Sato:
    • Hirata:
    • Shoda:
    • Fujii:
    • Tanaka:
    • Terrence:

Next meeting

On 2019/7/5(Fri)