Line 24: Line 24:
=== OMMT & OSTM === === OMMT & OSTM (Takahashi) ===
Line 26: Line 26:
 * Asking quotations for some modification parts for the mirror gluing jig and the standoff.
 * Preparing for shipping of the suspension.
 * The mirror will be ready in October.
Line 27: Line 30:
 * Test the OSEMs at the site.
 * Confirm some dimensions on the present OMMT/OSTM suspensions.

Agenda/Minutes of the VIS Meeting on 2019/7/12

2019/7/12 13:30 -

Zoom Meeting

Participants:

Progress report

Type-A

Past week report

  • Updated the Real-time model & medm for the Type-A payload.

  • Study on the deformation of base plate in the GAS filter with the ATC staff.

Plan for coming weeks

Type B

Past week report

Plan for coming weeks

Type-Bp

Past week report

Plan for coming weeks

OMMT & OSTM (Takahashi)

Past week report

  • Asking quotations for some modification parts for the mirror gluing jig and the standoff.
  • Preparing for shipping of the suspension.
  • The mirror will be ready in October.

Plan for coming weeks

  • Test the OSEMs at the site.
  • Confirm some dimensions on the present OMMT/OSTM suspensions.

VIS electronics

Past week report

Plan for coming weeks

Other site works

Safety

  • Incidents:

Discussion

Travel Plans

  • Travel (Week of 7/15):
    • Takahashi:
    • Sato:
    • Hirata:
    • Shoda:
    • Fujii:
    • Tanaka:
    • Terrence:
  • Travel (Week of 7/22):
    • Takahashi:
    • Sato:
    • Hirata:
    • Shoda:
    • Fujii:
    • Tanaka:
    • Terrence:

Next meeting

On 2019/7/19(Fri)