Agenda/Minutes of the VIS Meeting on 2019/7/26

2019/7/26 14:00 -

Zoom Meeting

Participants:

Progress report

Type-A

Past week report

  • Moved the SF/BF prototypes from the warehouse of TAMA to the ATC as the references for new design. Opened the cups and then found that the blades in the oldest prototype were broken.

Plan for coming weeks

Type B

Past week report

Plan for coming weeks

Type-Bp

Past week report

Plan for coming weeks

OMMT & OSTM (Takahashi)

Past week report

  • The standoffs have been delivered. Inspecting the sharpness of notch.
  • Designing the bottom spacer and the connector plate.

Plan for coming weeks

VIS electronics

Past week report

Plan for coming weeks

Other site works

Safety

  • Incidents:

Discussion

Travel Plans

  • Travel (Week of 7/29):
    • Takahashi: (Vacation)
    • Sato:
    • Hirata:
    • Shoda:
    • Fujii:
    • Tanaka:
  • Travel (Week of 8/5):
    • Takahashi: 6-8
    • Sato:
    • Hirata:
    • Shoda:
    • Fujii:
    • Tanaka:

Next meeting

On 2019/8/2(Fri)

KAGRA/Subgroups/VIS/VISMinutes20190725 (last edited 2019-07-26 15:29:16 by YoichiAso)