2019/9/20 14:00 - | 2019/9/20 14:00 - 14:59 |
Line 7: | Line 7: |
Participants: | Participants: Takahashi, Tanaka, Ishizaki, Fujii, Sato, Aso, Shoda, Hirata, Terrence, Lucia [[https://paper.dropbox.com/doc/VIS-Commissioning-Task-List--AlK26n6oP8QHU_XUQriwv2PvAg-RKcNXfMFrqOtTAPU48qQf|VIS Commissioning Task List]] [[https://onedrive.live.com/view.aspx?resid=8E8081C20FE5EC3A!2278&ithint=file%2cxlsx&authkey=!AMFNtNa-Y6CVp94|Post-O3 task list]] |
Line 20: | Line 24: |
* Oplev diagonalization on PRM | * Oplev diagonalization on PRM ([[http://klog.icrr.u-tokyo.ac.jp/osl/?r=10635|klog]]) |
Line 46: | Line 50: |
* Fujii: | * Fujii: 9/23 - |
Line 54: | Line 58: |
* Fujii: | * Fujii: - 9/30 |
Agenda/Minutes of the VIS Meeting on 2019/9/20
2019/9/20 14:00 - 14:59
Participants: Takahashi, Tanaka, Ishizaki, Fujii, Sato, Aso, Shoda, Hirata, Terrence, Lucia
Progress report
Type-A
Past week report
Plan for coming weeks
Type B
Past week report
Plan for coming weeks
Type-Bp
Past week report
Oplev diagonalization on PRM (klog)
Plan for coming weeks
OMMT & OSTM (Takahashi)
Past week report
- Evaluating the M2052 sample bar for OMC.
Plan for coming weeks
VIS electronics
Past week report
Plan for coming weeks
Other site works
Safety
- Incidents:
Discussion
- Continued discussion on the VIS repair/upgrade work between O3 and O4
Travel Plans
- Travel (Week of 9/23):
- Takahashi:
- Sato:
- Hirata:
- Shoda:
- Fujii: 9/23 -
- Tanaka:
- Travel (Week of 9/30):
- Takahashi:
- Sato:
- Hirata:
- Shoda:
- Fujii: - 9/30
- Tanaka:
Next meeting
On 2019/9/27(Fri)