⇤ ← Revision 1 as of 2019-11-01 09:47:25
Size: 1211
Comment:
|
Size: 1488
Comment:
|
Deletions are marked like this. | Additions are marked like this. |
Line 26: | Line 26: |
=== OMMT & OSTM === | === OMMT & OSTM (Takahashi) === |
Line 28: | Line 28: |
* M2052 bars for OMC are under ECB process. | |
Line 29: | Line 30: |
* Assembly and test of the OSTM suspension. * The mirror will be ready with the first contact. |
|
Line 40: | Line 43: |
* Time slots in the next F2F meeting: Request two slots (commissioning by Okutomi and future plan by Takahashi) | |
Line 43: | Line 47: |
* Takahashi: * Sato: |
* Takahashi: 5-7 * Sato: 5-7 |
Agenda/Minutes of the VIS Meeting on 2019/11/1
2019/11/1 14:00 -
Participants:
Progress report
Type-A
Past week report
Plan for coming weeks
Type B
Past week report
Plan for coming weeks
Type-Bp
Past week report
Plan for coming weeks
OMMT & OSTM (Takahashi)
Past week report
- M2052 bars for OMC are under ECB process.
Plan for coming weeks
- Assembly and test of the OSTM suspension.
- The mirror will be ready with the first contact.
VIS electronics
Past week report
Plan for coming weeks
Other site works
Safety
- Incidents:
Discussion
- Time slots in the next F2F meeting: Request two slots (commissioning by Okutomi and future plan by Takahashi)
Travel Plans
- Travel (Week of 11/4):
- Takahashi: 5-7
- Sato: 5-7
- Hirata:
- Shoda:
- Fujii:
- Tanaka:
- Travel (Week of 11/11):
- Takahashi:
- Sato:
- Hirata:
- Shoda:
- Fujii:
- Tanaka:
Next meeting
On 2019/11/8(Fri)