Line 2: Line 2:
2019/11/15 14:00 -  2019/11/15 14:00 -
Line 6: Line 6:
Participants:  Participants:
Line 10: Line 10:
[[https://onedrive.live.com/view.aspx?resid=8E8081C20FE5EC3A!2278&ithint=file,xlsx&authkey=!AMFNtNa-Y6CVp94|Post-O3 task list]]
[[https://www.dropbox.com/s/9l1h0fw9kc1pzmm/Proocurement%202019FY.xlsx?dl=0|Procurement list in 2019FY]]
[[https://onedrive.live.com/view.aspx?resid=8E8081C20FE5EC3A!2278&ithint=file,xlsx&authkey=!AMFNtNa-Y6CVp94|Post-O3 task list]] [[https://www.dropbox.com/s/9l1h0fw9kc1pzmm/Proocurement%202019FY.xlsx?dl=0|Procurement list in 2019FY]]
Line 19: Line 18:
Information about Type B suspensions fishing rods were compiled [[http://gwwiki.icrr.u-tokyo.ac.jp/JGWwiki/KAGRA/Subgroups/VIS/OpsManual/FishingRods|here]]. We stil need to compile the corresponding information from the other suspensions.
Line 23: Line 24:
=== OMMT & OSTM (Takahashi) === === OMMT & OSTM ===
Line 25: Line 26:
 * The OSTM mirror is ready with first-contact.
Line 26: Line 29:
 * Installation of the OSTM suspension is planed in the end of November.
Line 34: Line 39:
 * Talk in JPS/ASJ meeting.
 * Requests for participating in LV(K) meeting in March 2020.
 * About sliders for disassemby jig (Hirata, Shoda)

Agenda/Minutes of the VIS Meeting on 2019/11/15

2019/11/15 14:00 -

Zoom Meeting

Participants:

VIS Commissioning Task List

Post-O3 task list Procurement list in 2019FY

Progress report

Type-A

Past week report

Plan for coming weeks

Type B

Past week report

Information about Type B suspensions fishing rods were compiled here. We stil need to compile the corresponding information from the other suspensions.

Plan for coming weeks

Type-Bp

Past week report

Plan for coming weeks

OMMT & OSTM

Past week report

  • The OSTM mirror is ready with first-contact.

Plan for coming weeks

  • Installation of the OSTM suspension is planed in the end of November.

VIS electronics

Past week report

Plan for coming weeks

Other site works

Safety

  • Incidents:

Discussion

  • Talk in JPS/ASJ meeting.
  • Requests for participating in LV(K) meeting in March 2020.
  • About sliders for disassemby jig (Hirata, Shoda)

Travel Plans

  • Travel (Week of 11/18):
    • Takahashi:
    • Sato:
    • Hirata:
    • Shoda:
    • Fujii:
    • Tanaka:
  • Travel (Week of 11/25):
    • Takahashi: 27-28
    • Sato:
    • Hirata:
    • Shoda:
    • Fujii:
    • Tanaka:

Next meeting

On 2019/11/22(Fri)