Agenda/Minutes of the VIS Meeting on 2019/11/22
2019/11/22 14:00 -
Participants:
Post-O3 task list Procurement list in 2019FY
Progress report
Type-A
Past week report
Shoda is working on the noise budgeting using the theoretical model. klog Though it should be confirmed further, it will be applied on other suspensions.
- Sato-san updated the 3D cad model for EXV.
Plan for coming weeks
Type B
Past week report
Plan for coming weeks
- Disassembly of the mirror hanging jig.
Type-Bp
Past week report
Plan for coming weeks
OMMT & OSTM
Past week report
- Trouble of H1 coil in OMMT1?
Plan for coming weeks
- Check the DGS for the control of OSTM suspension.
VIS electronics
Past week report
Plan for coming weeks
Other site works
Safety
- Incidents:
Discussion
Guardian. See this link. (Fabian)
- New control scheme (Terrence).
Travel Plans
- Travel (Week of 11/25):
- Takahashi: 27-28
- Sato:
- Hirata: 27-28
- Shoda:
- Fujii:
- Tanaka:
- Travel (Week of 12/2):
- Takahashi:
- Sato: 3-4(ICRR Kashiwa)
- Hirata:
- Shoda:
- Fujii:
- Tanaka:
Next meeting
On 2019/11/29(Fri)