= Agenda/Minutes of the VIS Meeting on 2019/11/29 = 2019/11/29 14:00 - [[https://zoom.us/j/203743987|Zoom Meeting]] Participants: Takahashi, Aso, Lucia, Fabian, Okutomi, Sato, Ishizaki, Shoda, Tanaka [[https://paper.dropbox.com/doc/VIS-Commissioning-Task-List--AlK26n6oP8QHU_XUQriwv2PvAg-RKcNXfMFrqOtTAPU48qQf|VIS Commissioning Task List]] [[https://onedrive.live.com/view.aspx?resid=8E8081C20FE5EC3A!2278&ithint=file,xlsx&authkey=!AMFNtNa-Y6CVp94|Post-O3 task list]] [[https://www.dropbox.com/s/9l1h0fw9kc1pzmm/Proocurement%202019FY.xlsx?dl=0|Procurement list in 2019FY]] == Progress report == === Type-A === ==== Past week report ==== * Sato-san started the design of limit switch for FR. * ETMX GAS control saturation problem ([[http://klog.icrr.u-tokyo.ac.jp/osl/?r=11831|klog#11831]]) * F0 and F1 GAS control got saturated. * The height of BF has changed by +50 um in this 1 week. * For a temporary workaround, I put setpoint values of the GAS DC control to avoid the saturation. ---> The BF height has lifted more up: +50 um -> + 105 um. * Control output offloading is needed with fishing rods. ---> To be arranged in a few days ==== Plan for coming weeks ==== === Type B === ==== Past week report ==== * I modified the real-time model in order to accomodate bandpass fillters and new DAQ channels. See [[http://gwwiki.icrr.u-tokyo.ac.jp/JGWwiki/http://klog.icrr.u-tokyo.ac.jp/osl/?r=11788|11788]]. * For the most part I used the same scheme as Type A. * As agreed in the previous meeting I added a matrix ramp switch in order to transit from velocity damping to bandpass filters. * The medm screen was modified accordingly. * I realized yesterday I hadn't added a monitor for the output of the new filters banks in the EUL basis. It's been added to the real-time model, it compiles but still has to be installed. * Real-time models for SR suspensionsmust be compiled and installed. * Together with Terrence I modified vistools in order to generate functions to manipulate added filter banks. See [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=11788|11788]]. * The future of vistools looks quite gray (the code is complicated, not commented and we don't know how to manipulate matrix switches). Some additions will likely be in regular Guardian. * I began adding code for the OBSERVATION state in a draft file. * There was an agreement with Okutomi-san to change Type B medm screens for something more illustrative of the signal paths. * The temperature in the BS area has increased. It's been lately between 23.7 and 23.8 degrees. The actuation on the top filter used to be -23,000 counts and is now -13,500 counts. * Yamada-kun and Yokozawa-san measured transfer functions from BS to DARM and calculated the noise contribution. See [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=11676|11676]], [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=11724|11724]], [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=11707|11707]]. * The results are affected by an error in the calibration and are yet to be corrected. * The contributions of TM_DAMP_L and TM_DAMP_Y were considered to be high. These filters are supposed to be off in OBSERVATION state. See this [[http://klog.icrr.u-tokyo.ac.jp/osl/uploads/11748_20191125213530_bstodarmbeforeimyrolloff.png|plot]]. * These filters were rolled-off and the a new estimation was calculated. See this other [[http://klog.icrr.u-tokyo.ac.jp/osl/uploads/11748_20191125213851_bstodarmafterimyrolloff.png|plot]]. * The roll-off of TM_DAMP_Y was conservative. * Ushiba-san turned off BS TM-L DAMP filter for the FPMI state ([[http://klog.icrr.u-tokyo.ac.jp/osl/?r=11783|11783]]). It may have been affecting the sensitivity. * For the purposes of ASC the diagonalization of the TM actuation with respect to the oplev was removed by commissioners and replaced by their own coil balancing and drivealign diagonalization. I couldn't find a klog for this * Hirata-san disassembled the mirror hanging jig and transported it to Mitaka. ==== Plan for coming weeks ==== * Compile and install SR real-time models. * People have begun to modify or turn off filters which are supposed to be off in OBSEVATION state, maybe I should aim to design the bandpass filters and then implement the Guardian OBSERVATION state. === Type-Bp === ==== Past week report ==== ==== Plan for coming weeks ==== === OMMT & OSTM === ==== Past week report ==== * Transported the OSTM mirror. ==== Plan for coming weeks ==== * Installation of the OSTM suspension (12/9-12). === VIS electronics === ==== Past week report ==== ==== Plan for coming weeks ==== === Other site works === === Safety === * Incidents: == Discussion == * [[https://www.dropbox.com/s/e0inlp006spuj4m/Schedule%20after%20O3.pdf?dl=0|Schedule afetr O3]] == Travel Plans == * Travel (Week of 12/2): * Takahashi: * Sato: 3-4(ICRR Kashiwa) * Hirata: * Shoda: * Fujii: * Tanaka: * Travel (Week of 12/9): * Takahashi: 9-12 * Sato: 9-12 * Hirata: * Shoda: * Fujii: * Tanaka: == Next meeting == On 2019/12/6(Fri)