Line 20: Line 20:
* Yamada-kun made a control noise projection from Type-A payload actuators to DARM. ([[http://klog.icrr.u-tokyo.ac.jp/osl/?r=12229|klog#12229]])  * Yamada-kun made a control noise projection from Type-A payload actuators to DARM. ([[http://klog.icrr.u-tokyo.ac.jp/osl/?r=12229|klog#12229]])
Line 23: Line 23:

 * Real-time model update
  * To add hierarchical hand-over paths for TM oplev signals
  * To add setpoint of the TM oplevs before being sent to damping/DC control filters

Agenda/Minutes of the VIS Meeting on 2019/12/20

2019/12/20 14:00 -

Zoom Meeting

Participants:

VIS Commissioning Task List

Post-O3 task list

Schedule afetr O3

Procurement list in 2019FY

Progress report

Type-A

Past week report

  • Yamada-kun made a control noise projection from Type-A payload actuators to DARM. (klog#12229)

Plan for coming weeks

  • Real-time model update
    • To add hierarchical hand-over paths for TM oplev signals
    • To add setpoint of the TM oplevs before being sent to damping/DC control filters

Type B

Report for the week 16-12-2019

  • Limit switch for IM picomotors: last meeting there were concerns about the pin 5 of the in-air cable being connected to shield and the case. The solution would be to use an unshielded cable. See updated slides in this link.

  • SR2 neighborhood clean room survey.
    • I didn't finish this week surveying the clean room. I realized I need more information about the position of the handrails in the 2nd floor. I will measure that on the 14th of January. If the analysis is required earlier another person can take over. I left some files in Dropbox here.

    • There's not much space available to extend the clean room by a lot without blocking valuable access into the +X arm. We will likely require to set the oplev optics outside of the clean booth.
  • Type-B and Type-Bp oplve survey: I went to the tunnel and took a look but, as expected, important features are hidden under aluminium foil covers. I will collect 3D CAD models for the main components.
  • I left a very humble TO DO list for commissioning here. I will do this when I come back depeding on the commissioning priorities. Nevertheless, in case anyone wants to do it, please feel free.

Plan for coming weeks

Type-Bp

Past week report

Plan for coming weeks

OMMT & OSTM

Past week report

Plan for coming weeks

VIS electronics

Past week report

Plan for coming weeks

Other site works

Safety

  • Incidents:

Discussion

Travel Plans

  • Travel (Week of 12/23):
    • Takahashi:
    • Sato:
    • Hirata: 22-24(Shift)
    • Shoda: 21-23(Shift)
    • Fujii:
    • Tanaka:
  • Travel (Week of 12/30):
    • Takahashi:
    • Sato:
    • Hirata:
    • Shoda:
    • Fujii:
    • Tanaka:

Next meeting

On 2019/12/27(Fri)

KAGRA/Subgroups/VIS/VISMinutes20191220 (last edited 2019-12-20 17:18:58 by RyutaroTakahashi)