Agenda/Minutes of the VIS Meeting on 2020/2/14
2020/2/14 14:00 -
Participants:
Progress report
Type-A
Past week report
- TF Yaw fishing rod prototype testing
Test was done. Limit switch works normally. (200Mbyte)
- But the movement of the switch lever has periodic fluctuations. The cause will be investigated.
Plan for coming weeks
Type B
Past week report
- Oplev box: I got information from Hagiwara-san and Ushiba-san.
- I will show the design I have.
Plan for coming weeks
Type-Bp
Past week report
Plan for coming weeks
OMMT & OSTM
Past week report
Plan for coming weeks
VIS electronics
Past week report
Plan for coming weeks
Other site works
Safety
Discussion
- Wire gluing in PR3.
- C2C request in 2020FY.
Travel Plans
- Travel (Week of 2/17):
- Takahashi:
- Sato: 19-21(shift)
- Hirata: 20-22(shift)
- Shoda: 18-20(shift)
- Fujii:
- Tanaka:
- Travel (Week of 2/24):
- Takahashi:
- Sato:
- Hirata:
- Shoda:
- Fujii:
- Tanaka:
Next meeting
On 2020/2/21(Fri)