Line 2: | Line 2: |
2020/2/21 14:00 - | 2020/2/21 14:00 - 16:00 |
Line 6: | Line 6: |
Participants: | Participants: Takahashi, Shoda, Tanaka, Akutsu, Fabian, Hirata, Aso |
Line 16: | Line 16: |
==== Past week report ==== | |
Line 17: | Line 18: |
==== Past week report ==== | |
Line 24: | Line 25: |
==== Past week report ==== | |
Line 26: | Line 28: |
==== Past week report ==== | |
Line 33: | Line 35: |
* Measured the TFs from the output of ACT to the before/after demodulator. * The TFs should be compared with the theoretical calculation. |
|
Line 38: | Line 43: |
* [[https://gwdoc.icrr.u-tokyo.ac.jp/DocDB/0092/E1809209/008/O4%20schedule%20200217.pdf|Uchiyama-san's schedule plan]] (linked by Shoda) |
Agenda/Minutes of the VIS Meeting on 2020/2/21
2020/2/21 14:00 - 16:00
Participants: Takahashi, Shoda, Tanaka, Akutsu, Fabian, Hirata, Aso
Progress report
Type-A
Past week report
- Enabled the one whitening filters for Oplevs for all Type-As.
Plan for coming weeks
Type B
Past week report
- The fiber scope was delivered. It had actually a head of 3.9mm in diameter. The fiber is a shape memory type.
Plan for coming weeks
Type-Bp
Past week report
- Enabled the two whitening filters for Oplevs for PR3 and PRM, and three for PR2.
- Some roll offs have been set.
Plan for coming weeks
OMMT & OSTM
Past week report
Plan for coming weeks
VIS electronics
Past week report
- Measured the TFs from the output of ACT to the before/after demodulator.
- The TFs should be compared with the theoretical calculation.
Plan for coming weeks
Other site works
Safety
Discussion
Uchiyama-san's schedule plan (linked by Shoda)
Travel Plans
- Travel (Week of 2/24):
- Takahashi:
- Sato:
- Hirata:
- Shoda:
- Fujii:
- Tanaka:
- Travel (Week of 3/2):
- Takahashi:
- Sato:
- Hirata:
- Shoda:
- Fujii:
- Tanaka:
Next meeting