Line 17: Line 17:
 * Analysis of the tie-rods for corrugated tube.
 * Revising the [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=5500|Type-A installation procedure]].
Line 32: Line 34:
 * Plan for the long OR brake
  *Update without opening the chambers.
   * Signal generator cards for the LVDT driver.
   * Release sensor monitor.
   * Additional filters for the LVDT combiner.
   * New Oplev covers,
  * Temperature control.
  * New control scheme.

Agenda/Minutes of the VIS Meeting on 2020/4/3

2020/4/3 14:00 -

Zoom Meeting

Participants:

VIS Commissioning Task List

Post-O3 task list

Schedule afetr O3

Progress report

Type-A

Past week report

Plan for coming weeks

Type B

Past week report

Plan for coming weeks

Type-Bp

Past week report

Plan for coming weeks

Type-C

Past week report

Plan for coming weeks

VIS electronics

Past week report

Plan for coming weeks

Safety

Discussion

  • Plan for the long OR brake
    • Update without opening the chambers.
      • Signal generator cards for the LVDT driver.
      • Release sensor monitor.
      • Additional filters for the LVDT combiner.
      • New Oplev covers,
    • Temperature control.
    • New control scheme.

Travel Plans

  • Travel (Week of 4/6):
    • Takahashi:
    • Sato:
    • Hirata:
    • Shoda:
    • Tanaka:
  • Travel (Week of 4/13):
    • Takahashi:
    • Sato:
    • Hirata:
    • Shoda:
    • Tanaka:

Next meeting

On 2020/4/10(Fri)