=== General === Miyo-kun is gathered information about LVDTs at [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=11597|JGW-T2011597]]. Feedback seems to be required. |
|
Line 17: | Line 20: |
Line 18: | Line 22: |
* For a summary of the current status of inertial damping in Type-B suspensions see the appendix (p14 onwards) in the [[https://1drv.ms/b/s!AoQaV1tdsEcUgc5MtkkqJv5fcCYBrw?e=TXSzu0|presentation]] shown the commissioning meeting on the 27th of Sepetember 2019. * In the context of writing a paper I gathered information about OSEMs and LVDTs and uploaded a document at : [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=11612|JGW-T2011612]], which I will be updating.Currently the content is * Linear ranges of 24 OSEMs and * Sensitivity of the six SRM OSEMS. * I gave feedback to Miyo-kun about LVDTs. |
|
Line 25: | Line 35: |
Line 27: | Line 38: |
== Controls == * Had a VIS control strategy meeting [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=11557|documents]] |
|
Line 30: | Line 45: |
Agenda/Minutes of the VIS Meeting on 2020/4/17
2020/4/17 14:00 -
Participants:
Progress report
General
Miyo-kun is gathered information about LVDTs at JGW-T2011597. Feedback seems to be required.
Type-A
Revising the Type-A installation procedure.
Type B
For a summary of the current status of inertial damping in Type-B suspensions see the appendix (p14 onwards) in the presentation shown the commissioning meeting on the 27th of Sepetember 2019.
In the context of writing a paper I gathered information about OSEMs and LVDTs and uploaded a document at : JGW-T2011612, which I will be updating.Currently the content is
- Linear ranges of 24 OSEMs and
- Sensitivity of the six SRM OSEMS.
- I gave feedback to Miyo-kun about LVDTs.
Type-Bp
Type-C
Electronics
Post O3 (4/21~)
- Papers (Type-B: Fabian, Type-A:?)
- Operation mode at the shutdown of KAGRA
Towards O3c
Controls
Had a VIS control strategy meeting documents
Safety
Discussion
Travel Plans
Next meeting
On 2020/4/24(Fri)