* KAGRA is still in the suspended mode. Only remote measurements are available until May 31st (Q-measurement by Fabian). * More activities in the control room and the site will be available from June 1st (Type-A measurement by Lucia). |
* KAGRA is still in the suspended mode. Only remote measurements are available until May 31st (Q-measurement by Fabian, Type-A measurement by Lucia). * More activities in the control room and the site will be available from June 1st (Noise budget by Ushiba). |
Line 24: | Line 24: |
* Post Obs. task has priority higher than task for O3c. Two weeks, at least, in June is assigned for the Post Obs. task. | * Post Obs. task has priority higher than task for O3c. Two weeks, at least, in June will be assigned for Post Obs. task. |
Agenda/Minutes of the VIS Meeting on 2020/5/29
2020/5/29 14:00 -
Participants:
Progress report
General
Type-A
Type-B
Type-Bp
Type-C
Controls
Electronics
Post O3
- KAGRA is still in the suspended mode. Only remote measurements are available until May 31st (Q-measurement by Fabian, Type-A measurement by Lucia).
- More activities in the control room and the site will be available from June 1st (Noise budget by Ushiba).
- Decision for O3c in Virgo will be done within two weeks (from EO). If O3c was decided, task for O3c will be available as well (e.g. Sensor correction for SRs).
- Post Obs. task has priority higher than task for O3c. Two weeks, at least, in June will be assigned for Post Obs. task.
- The site work towards O4 will be rescheduled.
Safety
Discussion
Travel Plans
Next meeting
- On 2020/6/5(Fri)