* KAGRA is still in the suspended mode. Only remote measurements are available until May 31st (Q-measurement by Fabian). * More activities in the control room and the site will be available from June 1st (Type-A measurement by Lucia). |
* KAGRA is still in the suspended mode. Only remote measurements are available until May 31st (Q-measurement by Fabian, Type-A measurement by Lucia). * More activities in the control room and the site will be available from June 1st (Noise budget by Ushiba). |
Line 24: | Line 24: |
* Post Obs. task has priority higher than task for O3c. Two weeks, at least, in June is assigned for the Post Obs. task. | * Post Obs. task has priority higher than task for O3c. Two weeks, at least, in June will be assigned for Post Obs. task. |
Line 26: | Line 26: |
* Post Obs. task ([[https://docs.google.com/spreadsheets/d/1w4q8OvX9E6nkYSgshLYLoZH5yvQXHvGmL1agux8ztx0/edit?usp=sharing|Request]]), Task for O3c ([[https://paper.dropbox.com/doc/Plan-for-the-long-OR-brake--AxxlJFvK1IGJjqrG5nfdHfGXAQ-KqexeqMaCA7DITFGxA5ih|Plan]], [[https://www.dropbox.com/s/hoadb73fdyah02c/Post-O3%20task.xlsx?dl=0|Sheet]]). | Post Obs. task ([[https://docs.google.com/spreadsheets/d/1w4q8OvX9E6nkYSgshLYLoZH5yvQXHvGmL1agux8ztx0/edit?usp=sharing|Request]]), Task for O3c ([[https://paper.dropbox.com/doc/Plan-for-the-long-OR-brake--AxxlJFvK1IGJjqrG5nfdHfGXAQ-KqexeqMaCA7DITFGxA5ih|Plan]], [[https://www.dropbox.com/s/hoadb73fdyah02c/Post-O3%20task.xlsx?dl=0|Sheet]]). |
Line 30: | Line 31: |
* Papers * Mechanics of Type-A tower + Cryo-payload: Shoda (on going) * Performance of Type-A: Lucia * Control of Type-A: Lucia? * Control (Sensor correction): Fujii * Type-B: Fabian (on going) * Personnel towards O4 * Takahashi supervises both teams. * Type-A team: Sato, Miyo, Takahashi, company person * Type-B/Bp team: Shoda(supervisor), Hirata, Fabian, Terrence, Washimi, company person |
Agenda/Minutes of the VIS Meeting on 2020/5/29
2020/5/29 14:00 -
Participants:
Progress report
General
Type-A
Type-B
Type-Bp
Type-C
Controls
Electronics
Post O3
- KAGRA is still in the suspended mode. Only remote measurements are available until May 31st (Q-measurement by Fabian, Type-A measurement by Lucia).
- More activities in the control room and the site will be available from June 1st (Noise budget by Ushiba).
- Decision for O3c in Virgo will be done within two weeks (from EO). If O3c was decided, task for O3c will be available as well (e.g. Sensor correction for SRs).
- Post Obs. task has priority higher than task for O3c. Two weeks, at least, in June will be assigned for Post Obs. task.
- The site work towards O4 will be rescheduled.
Post Obs. task (Request), Task for O3c (Plan, Sheet).
Safety
Discussion
- Papers
- Mechanics of Type-A tower + Cryo-payload: Shoda (on going)
- Performance of Type-A: Lucia
- Control of Type-A: Lucia?
- Control (Sensor correction): Fujii
- Type-B: Fabian (on going)
- Personnel towards O4
- Takahashi supervises both teams.
- Type-A team: Sato, Miyo, Takahashi, company person
- Type-B/Bp team: Shoda(supervisor), Hirata, Fabian, Terrence, Washimi, company person
Travel Plans
Next meeting
- On 2020/6/5(Fri)