= Agenda/Minutes of the VIS Meeting on 2020/5/29 = 2020/5/29 14:00 - [[https://zoom.us/j/203743987|Zoom Meeting]] Participants: Takahashi, Fabian, Sato, Hirata, Shoda, Miyo, Tanaka, Aso, Lucia, Washimi [[https://onedrive.live.com/view.aspx?resid=8E8081C20FE5EC3A!2278&ithint=file,xlsx&authkey=!AMFNtNa-Y6CVp94|Task list towards O4]] [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=11475|Schedule towards O4]] == Progress report == === General === === Type-A === * As reported by Yamamoto-san ( see klog http://klog.icrr.u-tokyo.ac.jp/osl/?r=14432) F1 GAS output was satured. So Yesterday I offloaded the GAS output by changing the offset on F1 and F2 (see klog http://klog.icrr.u-tokyo.ac.jp/osl/?r=14434) * I took advantage of the suspended mode of KAGRA to investigate some strange response of the geophone installed on the Type A suspension. The test has been done with EX geophone. Basically, I changed the cutoff of the calibration filter from 10 mHz to 3 mHz and I measured the TF= GEO/(LVDT*w). By moving back to 3 mHz the DC cutoff the phase shift is reduced a lot, but the DC noise is growing up. I turned on the ID with blending at 140 mHz: the loop is stable, but the 148 mHz peack got excited (see klog http://klog.icrr.u-tokyo.ac.jp/osl/?r=14443). === Type-B === * I worked in the measurements of the decay times of SR2. I still have to analyze data. No results to show yet. * Washimi-san reported the feedback signal in SRM F0 was too high. I offloaded onto the fishing rod this morning (klog entry [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=14436|14436]]). According to the [[http://gwwiki.icrr.u-tokyo.ac.jp/JGWwiki/KAGRA/Subgroups/VIS/OpsManual/FishingRods|VIS wilki fishing rod page]], this fishing rod does not suffer of any known problems. * I will postpone asking questions about inertial damping again for next week. === Type-Bp === === Type-C === * 3D CAD model of the present IMMT2 suspension is completed. === Controls === * Working on the Type-A situation reproduction, which was assigned at cryo-payload upgrade review. (Shoda) * Comparing the IP performance from the design. === Electronics === * Test parts have been delivered. * The experiment will start from the week after next week. * Test of the LVDT card modification on the grounding is planed. == Post O3 == * KAGRA is still in the suspended mode. Only remote measurements are available until May 31st (Q-measurement by Fabian, Type-A measurement by Lucia). * More activities in the control room and the site will be available from June 1st (Noise budget by Ushiba). * Decision for O3c in Virgo will be done within two weeks (from EO). If O3c was decided, task for O3c will be available as well (e.g. Sensor correction for SRs). * Post Obs. task has priority higher than task for O3c. Two weeks, at least, in June will be assigned for Post Obs. task. * The site work towards O4 will be rescheduled. Post Obs. task ([[https://docs.google.com/spreadsheets/d/1w4q8OvX9E6nkYSgshLYLoZH5yvQXHvGmL1agux8ztx0/edit?usp=sharing|Request]]), Task for O3c ([[https://paper.dropbox.com/doc/Plan-for-the-long-OR-brake--AxxlJFvK1IGJjqrG5nfdHfGXAQ-KqexeqMaCA7DITFGxA5ih|Plan]], [[https://www.dropbox.com/s/hoadb73fdyah02c/Post-O3%20task.xlsx?dl=0|Sheet]]). == Safety == == Discussion == * Papers * Mechanics of Type-A tower + Cryo-payload: Shoda (on going) * Performance of Type-A: Lucia * Control of Type-A: Lucia? * Control (Sensor correction): Fujii * Type-B: Fabian (on going) * Personnel towards O4 * Takahashi supervises both teams. * Type-A team: Sato, Miyo, Takahashi, company person * Type-B/Bp team: Shoda(supervisor), Hirata, Fabian, Terrence, Washimi, company person == Travel Plans == == Next meeting == * On 2020/6/5(Fri)