Agenda/Minutes of the VIS Meeting on 2020/6/5

2020/6/5 14:00 -

Zoom Meeting

Participants:

Task list towards O4

Schedule towards O4

Progress report

General

Type-A

Type-B

Type-Bp

Type-C

Controls

Electronics

Post O3

  • More activities in the control room and the site became available from June 1st (Noise budget measurement by Ushiba).
  • O3c has not been decided yet, but the situation is going to O4 directly.
  • The site work towards O4 is rescheduled. The extended chief meeting will be held on June 15th to discuss about the plan towards O4.

Post Obs. task (Request), Task for O3c (Plan, Sheet).

Safety

Discussion

Travel Plans

Next meeting

  • On 2020/6/12(Fri)