= Agenda/Minutes of the VIS Meeting on 2020/6/5 = 2020/6/5 14:00 - [[https://zoom.us/j/203743987|Zoom Meeting]] Participants: Takahashi, Fabian, Sato, Hirata, Aso, Shoda, Lucia, Ishizaki, Tanaka, Miyo [[https://onedrive.live.com/view.aspx?resid=8E8081C20FE5EC3A!2278&ithint=file,xlsx&authkey=!AMFNtNa-Y6CVp94|Task list towards O4]] [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=11475|Schedule towards O4]] == Progress report == === General === * Because of Nakano-san and Miyoki-san's request, Miyo made VIS_MANAGER guardian to monitor and manage all suspensions. [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=14469|klog14469]] * Now, this guardian requests the all suspensions to go PAY_LOCAL_DAMPED state for safety when an earthquake hits. * but, there are no big earthquakes from this work. When big earthquakes happen, I will check and modify this guardian. === Type-A === === Type-B === * Fabian analyzed data of the SR2 suspension decay times with the control system on. Almost done but no plot to show yet. * On Thursday I helped Ushiba-san and Yokozawa-san to measure the BS oplev QPDs dark noise. See klog entry [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=14473|14473]]. * No questions about inertial damping today. === Type-Bp === === Type-C === === Controls === * Type-A modeling (Shoda) * (for the paper) Searching for the fastest way to derive the theoretical spring constant of the actual HLs. * (for the cryo-p evaluation) The RT model is updated. Need update of the actuation efficiency. === Electronics === * Started measurements of the circuits. It takes much time due to many variations of inductor. == Post O3 == * More activities in the control room and the site became available from June 1st (Noise budget measurement by Ushiba). * O3c has not been decided yet, but the situation is going to O4 directly. * The site work towards O4 is rescheduled. The extended chief meeting will be held on June 15th to discuss about the plan towards O4. * Tasks on electronics should be combined to the task list towards O4. * Procedure of the wire gluing should be confirmed beforehand. * Schedule including the commissioning should be considered, but overall plan and schedule, which will be discussed in the next SEO/Chief meeting, are necessary to make detail schedule. Post Obs. task ([[https://docs.google.com/spreadsheets/d/1w4q8OvX9E6nkYSgshLYLoZH5yvQXHvGmL1agux8ztx0/edit?usp=sharing|Request]]), Task for O3c ([[https://paper.dropbox.com/doc/Plan-for-the-long-OR-brake--AxxlJFvK1IGJjqrG5nfdHfGXAQ-KqexeqMaCA7DITFGxA5ih|Plan]], [[https://www.dropbox.com/s/hoadb73fdyah02c/Post-O3%20task.xlsx?dl=0|Sheet]]). == Safety == == Discussion == * Papers * Type-A: Lucia discussed with Fujii-san. * Type-B: Fabian discussed with the previous Type-B team. == Travel Plans == == Next meeting == * On 2020/6/12(Fri)