⇤ ← Revision 1 as of 2020-06-11 10:02:55
Size: 1349
Comment:
|
Size: 1350
Comment:
|
Deletions are marked like this. | Additions are marked like this. |
Line 21: | Line 21: |
* [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=11475|Revised schedule towards O4]] * [[https://www.dropbox.com/s/60oygtwmckmdyj6/Towards%20O4%20on%20VIS%20.xlsx?dl=0|Revised task list towards O4]] |
* [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=11475|Revised schedule towards O4]]. * [[https://www.dropbox.com/s/60oygtwmckmdyj6/Towards%20O4%20on%20VIS%20.xlsx?dl=0|Revised task list towards O4]]. |
Line 24: | Line 24: |
cf.: Post Obs. task ([[https://docs.google.com/spreadsheets/d/1w4q8OvX9E6nkYSgshLYLoZH5yvQXHvGmL1agux8ztx0/edit?usp=sharing|Request]]), Task for O3c ([[https://paper.dropbox.com/doc/Plan-for-the-long-OR-brake--AxxlJFvK1IGJjqrG5nfdHfGXAQ-KqexeqMaCA7DITFGxA5ih|Plan]], [[https://www.dropbox.com/s/hoadb73fdyah02c/Post-O3%20task.xlsx?dl=0|Sheet]]). | cf. Post Obs. task ([[https://docs.google.com/spreadsheets/d/1w4q8OvX9E6nkYSgshLYLoZH5yvQXHvGmL1agux8ztx0/edit?usp=sharing|Request]]), Task for O3c ([[https://paper.dropbox.com/doc/Plan-for-the-long-OR-brake--AxxlJFvK1IGJjqrG5nfdHfGXAQ-KqexeqMaCA7DITFGxA5ih|Plan]], [[https://www.dropbox.com/s/hoadb73fdyah02c/Post-O3%20task.xlsx?dl=0|Sheet]]). |
Agenda/Minutes of the VIS Meeting on 2020/6/12
2020/6/12 14:00 -
Participants:
Progress report
General
Type-A
Type-B
Type-Bp
Type-C
Controls
Electronics
Post O3
- Post Obs. tasks are on going. Decay time measurement in SR2 was performed. Sensor correction for SRs and SR suspension update are planed in the next week.
- O3c has not been decided yet, but the situation is going to O4 directly.
- The site work towards O4 is rescheduled. The extended chief meeting will be held on June 15th to discuss about the plan towards O4.
cf. Post Obs. task (Request), Task for O3c (Plan, Sheet).
Safety
Discussion
Travel Plans
Next meeting
- On 2020/6/17(Fri)