* As preparation for the control upgrade next week Miyo-kun and Fabian will modify the Type-B real-time model. It seems the modification is simple enough to do it remotely and we will ask Nakano-kun to restart the model after compilation. It only implies copying, pasting and renaming a few blocks. We received advice from Yamamoto-kun about the status of the connection of the IXV semsometer to the Dolphin network via the LSC model. |
Agenda/Minutes of the VIS Meeting on 2020/6/12
2020/6/12 14:00 -
Participants:
Progress report
General
Type-A
Type-B
The decay times measurement were finished. See klog 14510 for details.
- As preparation for the control upgrade next week Miyo-kun and Fabian will modify the Type-B real-time model. It seems the modification is simple enough to do it remotely and we will ask Nakano-kun to restart the model after compilation. It only implies copying, pasting and renaming a few blocks. We received advice from Yamamoto-kun about the status of the connection of the IXV semsometer to the Dolphin network via the LSC model.
Type-Bp
Type-C
Controls
Electronics
Post O3
- Post Obs. tasks are on going. Decay time measurement in SR2 was performed in this week. Sensor correction for SRs and SR suspension update are planed in the next week.
- O3c has not been decided yet, but the situation is going to O4 directly.
- The site work towards O4 is rescheduled. The extended chief meeting will be held on June 15th to discuss about the plan towards O4.
cf. Post Obs. task (Request), Task for O3c (Plan, Sheet).
Safety
Discussion
Travel Plans
Next meeting
- On 2020/6/17(Fri)