Line 10: | Line 10: |
* I started to prepare the heater jackets for temperature control of GAS. This project doesn't have a time schedule. [[https://github.com/gw-vis/kagra-vis/issues/20| (Github Issue)]] | * I started to prepare the heater jackets for temperature control of GAS. This project doesn't have a time schedule. We have to discuss. [[https://github.com/gw-vis/kagra-vis/issues/20| (Github Issue)]] |
Agenda/Minutes of the VIS Meeting on 2020/6/26
2020/6/26 14:00 -
Participants:
Progress report
General
I started to prepare the heater jackets for temperature control of GAS. This project doesn't have a time schedule. We have to discuss. (Github Issue)
Type-A
Type-B
Type-Bp
Type-C
Controls
Electronics
Post O3
- Post Obs. tasks are on going. Decay time measurements were carried out again. RT model modification for other Type-Bs is planed in this weekend. Sensor correction for SRs and SR suspension update will be started from July.
- O3c will be canceled.
Task towards O4 (List) was revised.
cf. Post Obs. task (Request), Task for O3c (Plan, Sheet), Schedule towards O4 (Chart).
Safety
Discussion
Travel Plans
Next meeting
- On 2020/7/3(Fri)